Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
278
matching recommendationsSIC | 32 | Stone, Clay, And Glass Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MS0139 # 01 Y:1999 | 01 | 1999 | USE PHOTOCELL CONTROLS | $3,484 | $490 | Not Implemented |
MS0139 # 02 Y:1999 | 02 | 1999 | INSTALL TIMERS AND/OR THERMOSTATS | $219 | $591 | Implemented |
MS0139 # 03 Y:1999 | 03 | 1999 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT INCOMING FLUIDS | $61,739 | $26,241 | Implemented |
MS0139 # 04 Y:1999 | 04 | 1999 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,224 | $554 | Implemented |
MS0139 # 05 Y:1999 | 05 | 1999 | REDUCE / ELIMINATE USE OF DISPOSABLE PRODUCT | $169 | $574 | Not Implemented |
UM0144 # 01 Y:1999 | 01 | 1999 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $1,661 | $110 | Implemented |
UM0144 # 02 Y:1999 | 02 | 1999 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $647 | $1,000 | Implemented |
UM0144 # 03 Y:1999 | 03 | 1999 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,285 | $350 | Implemented |
UM0144 # 04 Y:1999 | 04 | 1999 | RE-SIZE CHARGING OPENINGS OR ADD A MOVABLE DOOR ON EQUIPMENT | $5,837 | $9,350 | Not Implemented |
UM0144 # 05 Y:1999 | 05 | 1999 | USE OPTIMUM THICKNESS INSULATION | $1,848 | $2,100 | Not Implemented |
UM0144 # 06 Y:1999 | 06 | 1999 | REDUCE SCRAP PRODUCTION | $29,091 | $5,000 | Implemented |
UM0144 # 07 Y:1999 | 07 | 1999 | $7,680 | $584 | Implemented | |
KU0518 # 01 Y:1999 | 01 | 1999 | USE WASTE HEAT FROM HOT FLUE GASES TO GENERATE STEAM | $15,510 | $29,690 | Not Implemented |
KU0518 # 02 Y:1999 | 02 | 1999 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,240 | $800 | Not Implemented |
KU0518 # 03 Y:1999 | 03 | 1999 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,010 | $770 | Not Implemented |
KU0518 # 04 Y:1999 | 04 | 1999 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $230 | $350 | Not Implemented |
KU0518 # 05 Y:1999 | 05 | 1999 | METER WASTE WATER | $2,620 | $1,900 | Not Implemented |
KU0518 # 06 Y:1999 | 06 | 1999 | USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION | $2,230 | $1,050 | Not Implemented |
KU0518 # 07 Y:1999 | 07 | 1999 | $3,650 | $10,000 | Not Implemented | |
GT0666 # 01 Y:1999 | 01 | 1999 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $30,744 | $35,000 | Implemented |
GT0666 # 02 Y:1999 | 02 | 1999 | ADJUST BURNERS FOR EFFICIENT OPERATION | $366,782 | $180,000 | Implemented |
GT0666 # 03 Y:1999 | 03 | 1999 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,440 | $450 | Implemented |
GT0666 # 04 Y:1999 | 04 | 1999 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $10,598 | $2,500 | Implemented |
GT0666 # 05 Y:1999 | 05 | 1999 | USE OPTIMUM SIZE AND CAPACITY EQUIPMENT | $30,735 | $8,017 | Not Implemented |
GT0666 # 06 Y:1999 | 06 | 1999 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $2,354 | $3,900 | Not Implemented |