Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
284
matching recommendationsSIC | 32 | Stone, Clay, And Glass Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UD0636 # 02 Y:2002 | 02 | 2002 | INSULATE BARE EQUIPMENT | $20,587 | $7,200 | Implemented |
UD0636 # 03 Y:2002 | 03 | 2002 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $20,230 | $25,000 | Implemented |
UD0636 # 04 Y:2002 | 04 | 2002 | OPTIMIZE PLANT POWER FACTOR | $4,987 | $3,750 | Implemented |
UD0636 # 05 Y:2002 | 05 | 2002 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $4,247 | $500 | Implemented |
UD0636 # 06 Y:2002 | 06 | 2002 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,668 | $1,185 | Implemented |
UD0636 # 07 Y:2002 | 07 | 2002 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,509 | $2,880 | Implemented |
UD0636 # 08 Y:2002 | 08 | 2002 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,335 | $420 | Implemented |
UD0636 # 09 Y:2002 | 09 | 2002 | USE HEAT IN FLUE GASES TO PREHEAT PRODUCTS OR MATERIALS | $1,223 | $0 | Implemented |
UD0636 # 10 Y:2002 | 10 | 2002 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $736 | $300 | Implemented |
UD0614 # 01 Y:2001 | 01 | 2001 | INCREASE USE OF AUTOMATION | $277,500 | $100,000 | Not Implemented |
UD0614 # 02 Y:2001 | 02 | 2001 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $53,184 | $30,570 | Implemented |
UD0614 # 03 Y:2001 | 03 | 2001 | USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION | $11,618 | $23,000 | Not Implemented |
UD0614 # 04 Y:2001 | 04 | 2001 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $10,036 | $0 | Not Implemented |
UD0614 # 05 Y:2001 | 05 | 2001 | TURN OFF EQUIPMENT WHEN NOT IN USE | $6,252 | $0 | Implemented |
UM0147 # 01 Y:1999 | 01 | 1999 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,038 | $3,557 | Not Implemented |
UM0147 # 02 Y:1999 | 02 | 1999 | UTILIZE A LESS EXPENSIVE COOLING METHOD | $4,796 | $2,000 | Not Implemented |
UM0147 # 03 Y:1999 | 03 | 1999 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $19,748 | $500 | Not Implemented |
UM0147 # 04 Y:1999 | 04 | 1999 | RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR | $7,215 | $10,000 | Not Implemented |
UM0147 # 05 Y:1999 | 05 | 1999 | RECOVER AND REUSE WASTE MATERIAL | $1,436 | $0 | Implemented |
UM0147 # 06 Y:1999 | 06 | 1999 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $990 | $400 | Not Implemented |
UD0577 # 01 Y:1999 | 01 | 1999 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $640,050 | $1,000,000 | Not Implemented |
UD0577 # 02 Y:1999 | 02 | 1999 | INSTALL EQUIPMENT TO MOVE PRODUCT | $320,742 | $525,000 | Not Implemented |
UD0577 # 03 Y:1999 | 03 | 1999 | EMPLOY MODULAR JIGS TO REDUCE PROCESS SET-UP TIME | $118,825 | $15,000 | Not Implemented |
UD0577 # 04 Y:1999 | 04 | 1999 | RECOVER AND REUSE WASTE MATERIAL | $88,813 | $200,000 | Not Implemented |
UD0577 # 05 Y:1999 | 05 | 1999 | INSTALL EQUIPMENT TO MOVE PRODUCT | $35,600 | $57,000 | Not Implemented |