150
matching recommendationsSIC | 3273 | Ready-mixed Concrete |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LE0570 # 01 Y:2024 | 01 | 2024 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $9,292 | $0 | Implemented |
LE0570 # 02 Y:2024 | 02 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $33,515 | $15,000 | Implemented |
LE0570 # 05 Y:2024 | 05 | 2024 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $4,252 | $5,000 | Implemented |
LE0570 # 06 Y:2024 | 06 | 2024 | INSTALL BACK-UP EQUIPMENT | $46,731 | $90,000 | Implemented |
LE0570 # 04 Y:2024 | 04 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $25,168 | $26,500 | Implemented |
LE0570 # 03 Y:2024 | 03 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $55,246 | $42,000 | Implemented |
UW2317 # 05 Y:2023 | 05 | 2023 | IMPROVE COMBUSTION CONTROL CAPABILITY | $30,104 | $300,000 | Implemented |
UW2317 # 04 Y:2023 | 04 | 2023 | CHANGE PRODUCT DESIGN TO REDUCE ENERGY REQUIREMENTS | $31,756 | $1,000,000 | Implemented |
UW2317 # 02 Y:2023 | 02 | 2023 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $658 | $1,096 | Implemented |
UW2317 # 03 Y:2023 | 03 | 2023 | INSTALL STORM WINDOWS AND DOORS | $156 | $1,901 | Implemented |
UW2317 # 01 Y:2023 | 01 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $533 | $0 | Implemented |
UW2315 # 02 Y:2023 | 02 | 2023 | IMPROVE COMBUSTION CONTROL CAPABILITY | $30,104 | $300,000 | Implemented |
UW2315 # 01 Y:2023 | 01 | 2023 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $6,189 | $1,896 | Implemented |
WM0204 # 02 Y:2023 | 02 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,440 | $2,330 | Implemented |
WM0204 # 04 Y:2023 | 04 | 2023 | INSTALL OCCUPANCY SENSORS | $571 | $750 | Implemented |
WM0204 # 05 Y:2023 | 05 | 2023 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $97 | $240 | Implemented |
IC0283 # 04 Y:2023 | 04 | 2023 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $350 | $840 | Implemented |
IC0283 # 02 Y:2023 | 02 | 2023 | INSTALL / REPAIR INSULATION ON STEAM LINES | $192 | $13 | Implemented |
IC0283 # 01 Y:2023 | 01 | 2023 | INSULATE BARE EQUIPMENT | $112 | $886 | Implemented |
UW2308 # 05 Y:2023 | 05 | 2023 | IMPROVE COMBUSTION CONTROL CAPABILITY | $47,887 | $200,000 | Implemented |
UW2308 # 04 Y:2023 | 04 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $206 | $1,815 | Implemented |
UW2308 # 06 Y:2023 | 06 | 2023 | CHANGE PRODUCT DESIGN TO REDUCE ENERGY REQUIREMENTS | $36,635 | $0 | Implemented |
UW2308 # 01 Y:2023 | 01 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,223 | $0 | Implemented |
UW2308 # 03 Y:2023 | 03 | 2023 | INSTALL STORM WINDOWS AND DOORS | $145 | $1,901 | Implemented |
UW2308 # 02 Y:2023 | 02 | 2023 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $491 | $1,096 | Implemented |