Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
86
matching recommendationsSIC | 329 | Misc. Nonmetallic Mineral Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
GT0762 # 06 Y:2003 | 06 | 2003 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $2,390 | $0 | Not Implemented |
GT0752 # 07 Y:2003 | 07 | 2003 | UPGRADE OBSOLETE EQUIPMENT | $129,140 | $1,200,000 | Implemented |
GT0752 # 06 Y:2003 | 06 | 2003 | ADD/MODIFY EQUIPMENT TO IMPROVE DRYING PROCESS | $1,221,000 | $0 | Not Implemented |
GT0752 # 05 Y:2003 | 05 | 2003 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $211,700 | $260,000 | Not Implemented |
GT0752 # 04 Y:2003 | 04 | 2003 | COVER OPEN TANKS | $308,000 | $361,000 | Implemented |
GT0752 # 03 Y:2003 | 03 | 2003 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $8,459 | $2,000 | Not Implemented |
GT0752 # 08 Y:2003 | 08 | 2003 | USE SMALL NUMBER OF HIGH OUTPUT UNITS INSTEAD OF MANY SMALL INEFFICIENT UNITS | $1,773,429 | $6,000,000 | n/a |
GT0752 # 02 Y:2003 | 02 | 2003 | IMPROVE LUBRICATION PRACTICES | $3,514 | $0 | Not Implemented |
GT0752 # 01 Y:2003 | 01 | 2003 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,786 | $500 | Implemented |
GT0752 # 09 Y:2003 | 09 | 2003 | USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT | $435,100 | $2,070,000 | Not Implemented |
GT0741 # 11 Y:2002 | 11 | 2002 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $223,500 | $100,000 | Not Implemented |
GT0741 # 01 Y:2002 | 01 | 2002 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $80,749 | $0 | Implemented |
GT0741 # 02 Y:2002 | 02 | 2002 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $204 | $0 | Not Implemented |
GT0741 # 03 Y:2002 | 03 | 2002 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $3,490 | $2,100 | Not Implemented |
GT0741 # 10 Y:2002 | 10 | 2002 | REUSE / RECYCLE/ SELL PAPER PRODUCTS | $3,600 | $6,700 | Implemented |
GT0741 # 09 Y:2002 | 09 | 2002 | ELIMINATE LEAKS IN WATER LINES AND VALVES | $14,600 | $0 | Not Implemented |
GT0741 # 08 Y:2002 | 08 | 2002 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $13,635 | $98,936 | Implemented |
GT0741 # 07 Y:2002 | 07 | 2002 | USE WASTE HEAT WITH A CLOSED-CYCLE GAS TURBINE-GENERATOR SET TO COGENERATE ELECTRICITY AND HEAT | $674,846 | $2,070,000 | Not Implemented |
GT0741 # 06 Y:2002 | 06 | 2002 | ADJUST BURNERS FOR EFFICIENT OPERATION | $268,450 | $200,000 | Not Implemented |
GT0741 # 05 Y:2002 | 05 | 2002 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $16,970 | $15,430 | Implemented |
GT0741 # 04 Y:2002 | 04 | 2002 | USE SYNTHETIC LUBRICANT | $9,470 | $0 | Not Implemented |
GT0727 # 07 Y:2002 | 07 | 2002 | INSULATE BARE EQUIPMENT | $147,500 | $181,000 | Not Implemented |
GT0727 # 06 Y:2002 | 06 | 2002 | REPLACE HEAT TREATING OVEN WITH MORE EFFICIENT UNIT | $679,000 | $250,000 | Not Implemented |
GT0727 # 05 Y:2002 | 05 | 2002 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $165,202 | $0 | Not Implemented |
GT0727 # 04 Y:2002 | 04 | 2002 | REDESIGN PROCESS | $2,159,550 | $0 | Implemented |