Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
37
matching recommendationsSIC | 3297 | Nonclay Refractories |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WV0528 # 10 Y:2016 | 10 | 2016 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $311 | $297 | Implemented |
WV0528 # 02 Y:2016 | 02 | 2016 | MINIMIZE OPERATION OF EQUIPMENT MAINTAINED IN STANDBY CONDITION | $10,411 | $5,250 | Implemented |
WV0528 # 03 Y:2016 | 03 | 2016 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $10,032 | $1,000 | Implemented |
WV0528 # 05 Y:2016 | 05 | 2016 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,004 | $325 | Implemented |
WV0528 # 07 Y:2016 | 07 | 2016 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,820 | $1,500 | Implemented |
WV0528 # 08 Y:2016 | 08 | 2016 | DEVELOP A REPAIR/REPLACE POLICY | $1,959 | $904 | Implemented |
WV0528 # 09 Y:2016 | 09 | 2016 | UPGRADE CONTROLS ON COMPRESSORS | $635 | $3,000 | Implemented |
UD0937 # 01 Y:2015 | 01 | 2015 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $8,087 | $0 | Implemented |
UD0937 # 03 Y:2015 | 03 | 2015 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $1,253 | $0 | Implemented |
UD0937 # 05 Y:2015 | 05 | 2015 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $114 | $150 | Implemented |
UD0937 # 09 Y:2015 | 09 | 2015 | DEVELOP A REPAIR/REPLACE POLICY | $330 | $1,911 | Implemented |
UD0937 # 10 Y:2015 | 10 | 2015 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $948 | $0 | Implemented |
UD0909 # 05 Y:2014 | 05 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $667 | $2,940 | Implemented |
UD0909 # 06 Y:2014 | 06 | 2014 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $11,214 | $5,000 | Implemented |
UD0909 # 07 Y:2014 | 07 | 2014 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,032 | $1,000 | Implemented |
UD0909 # 09 Y:2014 | 09 | 2014 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $797 | $0 | Implemented |
UD0909 # 10 Y:2014 | 10 | 2014 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $797 | $0 | Implemented |
UD0909 # 02 Y:2014 | 02 | 2014 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $1,680 | $1,125 | Implemented |
UD0901 # 05 Y:2014 | 05 | 2014 | REDUCE FLUID FLOW RATES | $151,019 | $100,000 | Implemented |
UD0901 # 04 Y:2014 | 04 | 2014 | RECOVER AND REUSE COOLING WATER | $221,902 | $100,000 | Implemented |
UD0901 # 10 Y:2014 | 10 | 2014 | REDUCE VENTILATION AIR | $31,388 | $33,025 | Implemented |
WV0348 # 01 Y:2006 | 01 | 2006 | PREHEAT COMBUSTION AIR WITH WASTE HEAT | $22,813 | $25,350 | Implemented |
WV0348 # 02 Y:2006 | 02 | 2006 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $14,538 | $3,000 | Implemented |
WV0348 # 04 Y:2006 | 04 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,642 | $8,678 | Implemented |
WV0348 # 07 Y:2006 | 07 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,260 | $0 | Implemented |