IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

748

matching recommendations
Reset
SIC 33 Primary Metal Industries
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
SF0289 # 08 Y:2004 08 2004 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,750 $6,748 Implemented
SF0289 # 09 Y:2004 09 2004 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $449 $960 Not Implemented
SF0289 # 10 Y:2004 10 2004 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE $7,873 $100 Not Implemented
LM0080 # 01 Y:2004 01 2004 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $621 $475 Implemented
LM0080 # 02 Y:2004 02 2004 REMOVE OR CLOSE OFF UNNEEDED COMPRESSED AIR LINES $266 $165 Not Implemented
LM0080 # 03 Y:2004 03 2004 ADJUST BURNERS FOR EFFICIENT OPERATION $537 $0 Implemented
LM0080 # 04 Y:2004 04 2004 RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS $28,600 $20,592 Not Implemented
LM0080 # 05 Y:2004 05 2004 REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES $3,467 $6,000 Not Implemented
LM0080 # 06 Y:2004 06 2004 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $23,164 $300 Implemented
LM0080 # 07 Y:2004 07 2004 UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT $869 $0 Not Implemented
LM0074 # 01 Y:2004 01 2004 INSULATE BARE EQUIPMENT $3,094 $231 Implemented
LM0074 # 02 Y:2004 02 2004 REDUCE COMBUSTION AIR FLOW TO OPTIMUM $1,288 $1,000 Implemented
LM0074 # 03 Y:2004 03 2004 PAY BILLS ON TIME TO AVOID LATE FEES $392 $0 Implemented
LM0074 # 04 Y:2004 04 2004 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,673 $125 Implemented
LM0074 # 05 Y:2004 05 2004 REPAIR AND ELIMINATE STEAM LEAKS $3,618 $4,000 Implemented
LM0074 # 06 Y:2004 06 2004 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,439 $1,740 Implemented
LM0074 # 07 Y:2004 07 2004 INSTALL SKYLIGHTS $2,237 $300 Not Implemented
LM0074 # 08 Y:2004 08 2004 TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY $21,938 $6,600 Implemented
LM0074 # 09 Y:2004 09 2004 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $431 $0 Not Implemented
LM0074 # 10 Y:2004 10 2004 MODIFY WORKLOAD $41,860 $19,000 Implemented
SF0279 # 01 Y:2004 01 2004 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $699 $0 Implemented
SF0279 # 02 Y:2004 02 2004 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $11,368 $11,810 Not Implemented
SF0279 # 03 Y:2004 03 2004 INSTALL OCCUPANCY SENSORS $1,168 $1,200 Not Implemented
SF0279 # 04 Y:2004 04 2004 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,520 $13,375 Implemented
SF0279 # 05 Y:2004 05 2004 OPTIMIZE PLANT POWER FACTOR $1,079 $1,376 Not Implemented