Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
10,344
matching recommendationsSIC | 33 | Primary Metal Industries |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AM0692 # 01 Y:2015 | 01 | 2015 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $12,970 | $10,000 | Implemented |
AM0692 # 02 Y:2015 | 02 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $11,830 | $5,000 | Implemented |
AM0692 # 03 Y:2015 | 03 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,880 | $16,750 | Implemented |
AM0692 # 04 Y:2015 | 04 | 2015 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $2,124 | $0 | Implemented |
AM0692 # 05 Y:2015 | 05 | 2015 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,115 | $0 | Implemented |
AM0692 # 06 Y:2015 | 06 | 2015 | USE SYNTHETIC LUBRICANT | $1,560 | $0 | Implemented |
AM0692 # 07 Y:2015 | 07 | 2015 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $870 | $6 | Implemented |
AM0692 # 08 Y:2015 | 08 | 2015 | DISCONNECT BALLASTS | $533 | $1,100 | Implemented |
AM0692 # 09 Y:2015 | 09 | 2015 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $480 | $10 | Implemented |
AM0691 # 01 Y:2015 | 01 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $25,140 | $39,720 | Not Implemented |
AM0691 # 02 Y:2015 | 02 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,550 | $2,000 | Implemented |
AM0691 # 03 Y:2015 | 03 | 2015 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,250 | $1,720 | Not Implemented |
AM0691 # 04 Y:2015 | 04 | 2015 | TURN OFF EQUIPMENT WHEN NOT IN USE | $440 | $0 | Implemented |
AM0691 # 05 Y:2015 | 05 | 2015 | INSTALL OCCUPANCY SENSORS | $420 | $240 | Not Implemented |
AM0691 # 06 Y:2015 | 06 | 2015 | USE PHOTOCELL CONTROLS | $280 | $130 | Implemented |
AM0691 # 07 Y:2015 | 07 | 2015 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $120 | $130 | Not Implemented |
BS0065 # 01 Y:2015 | 01 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $18,229 | $46,340 | Implemented |
BS0065 # 02 Y:2015 | 02 | 2015 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $4,215 | $10,715 | Not Implemented |
BS0065 # 03 Y:2015 | 03 | 2015 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $5,088 | $160 | Implemented |
BS0065 # 04 Y:2015 | 04 | 2015 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $148 | $15 | Implemented |
OK0923 # 01 Y:2015 | 01 | 2015 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,384 | $754 | Not Implemented |
OK0923 # 02 Y:2015 | 02 | 2015 | REPAIR AND ELIMINATE STEAM LEAKS | $1,094 | $0 | Implemented |
OK0923 # 03 Y:2015 | 03 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $975 | $7,410 | Implemented |
OK0923 # 04 Y:2015 | 04 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $37,605 | $98,298 | Implemented |
OK0923 # 05 Y:2015 | 05 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,611 | $8,405 | Implemented |