Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
190
matching recommendationsSIC | 33 | Primary Metal Industries |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IP0031 # 03 Y:2014 | 03 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,679 | $59,914 | Implemented |
IP0031 # 01 Y:2014 | 01 | 2014 | USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION | $5,065,497 | $375,000 | Not Implemented |
IP0031 # 05 Y:2014 | 05 | 2014 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,661,000 | $17,500,000 | Not Implemented |
IP0031 # 04 Y:2014 | 04 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,588 | $22,450 | Implemented |
IP0031 # 02 Y:2014 | 02 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $22,715 | $14,486 | Implemented |
UD0916 # 10 Y:2014 | 10 | 2014 | UPGRADE CONTROLS ON COMPRESSORS | $10,562 | $110,000 | Implemented |
UD0916 # 12 Y:2014 | 12 | 2014 | CONTRACT A WOOD PALLET RECYCLING COMPANY | $12,800 | $0 | Implemented |
UD0916 # 08 Y:2014 | 08 | 2014 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $896 | $0 | Not Implemented |
UD0916 # 09 Y:2014 | 09 | 2014 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,978 | $1,000 | Implemented |
UD0916 # 11 Y:2014 | 11 | 2014 | ENHANCE SENSITIVITY OF TEMPERATURE CONTROL AND CUTOFF | $9,661 | $40,000 | Not Implemented |
UD0916 # 07 Y:2014 | 07 | 2014 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,426 | $4,150 | Not Implemented |
UD0916 # 01 Y:2014 | 01 | 2014 | TURN OFF EQUIPMENT WHEN NOT IN USE | $5,270 | $0 | Not Implemented |
UD0916 # 05 Y:2014 | 05 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $14,413 | $26,040 | Not Implemented |
UD0916 # 02 Y:2014 | 02 | 2014 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,027 | $0 | Not Implemented |
UD0916 # 06 Y:2014 | 06 | 2014 | INSTALL OCCUPANCY SENSORS | $503 | $500 | Implemented |
UD0916 # 03 Y:2014 | 03 | 2014 | INSTALL MOTOR VOLTAGE CONTROLLER ON LIGHTLY LOADED MOTORS | $6,076 | $11,700 | Not Implemented |
UD0916 # 04 Y:2014 | 04 | 2014 | RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER | $25,351 | $43,280 | Not Implemented |
TT0142 # 03 Y:2014 | 03 | 2014 | INSTALL / REPAIR INSULATION ON STEAM LINES | $861 | $1,662 | Not Implemented |
TT0142 # 05 Y:2014 | 05 | 2014 | DISCONNECT BALLASTS | $555 | $60 | Not Implemented |
TT0142 # 06 Y:2014 | 06 | 2014 | USE PHOTOCELL CONTROLS | $49 | $45 | Implemented |
TT0142 # 04 Y:2014 | 04 | 2014 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $11,651 | $3,000 | Implemented |
TT0142 # 01 Y:2014 | 01 | 2014 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $2,305 | $1,400 | Implemented |
TT0142 # 02 Y:2014 | 02 | 2014 | INSTALL / REPAIR INSULATION ON STEAM LINES | $299 | $596 | Not Implemented |
WV0496 # 02 Y:2014 | 02 | 2014 | REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES | $35,349 | $61,000 | Not Implemented |
WV0496 # 01 Y:2014 | 01 | 2014 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $46,701 | $10,800 | Not Implemented |