Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
31
matching recommendationsSIC | 3321 | Gray And Ductile Iron Foundries |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UD0608 # 04 Y:2000 | 04 | 2000 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $4,480 | $14,755 | Implemented |
UD0608 # 03 Y:2000 | 03 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,027 | $6,250 | Implemented |
UD0608 # 02 Y:2000 | 02 | 2000 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $13,231 | $1,200 | Implemented |
UD0608 # 01 Y:2000 | 01 | 2000 | REPLACE CITY WATER WITH RECYCLED WATER VIA COOLING TOWER | $27,415 | $15,000 | Implemented |
UM0169 # 06 Y:2000 | 06 | 2000 | USE RADIANT HEATER FOR SPOT HEATING | $8,102 | $10,000 | Implemented |
UM0169 # 05 Y:2000 | 05 | 2000 | RECOVER WASTE HEAT FROM EQUIPMENT | $2,117 | $500 | Implemented |
UM0169 # 02 Y:2000 | 02 | 2000 | INSTALL OCCUPANCY SENSORS | $1,322 | $800 | Implemented |
UM0169 # 01 Y:2000 | 01 | 2000 | $15,444 | $2,250 | Implemented | |
UM0169 # 08 Y:2000 | 08 | 2000 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $50,433 | $23,500 | Implemented |
UM0168 # 01 Y:2000 | 01 | 2000 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $526 | $993 | Implemented |
UM0168 # 03 Y:2000 | 03 | 2000 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $24,945 | $2,250 | Implemented |
UM0168 # 04 Y:2000 | 04 | 2000 | UPGRADE CONTROLS ON COMPRESSORS | $8,180 | $300 | Implemented |
WV0194 # 07 Y:2000 | 07 | 2000 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $2,231 | $1,280 | Implemented |
WV0194 # 04 Y:2000 | 04 | 2000 | INSTALL PARTITIONS TO REDUCE SIZE OF CONDITIONED SPACE | $1,330 | $210 | Implemented |
WV0194 # 12 Y:2000 | 12 | 2000 | $15,000 | $5,824 | Implemented | |
WV0194 # 05 Y:2000 | 05 | 2000 | REPAIR FURNACES AND OVEN DOORS SO THAT THEY SEAL EFFICIENTLY | $2,224 | $460 | Implemented |
WV0194 # 08 Y:2000 | 08 | 2000 | USE INSULATION IN FURNACES TO FACILITATE HEATING / COOLING | $4,605 | $5,330 | Implemented |
ND0346 # 09 Y:2000 | 09 | 2000 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,454 | $750 | Implemented |
ND0346 # 10 Y:2000 | 10 | 2000 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $238 | $60 | Implemented |
ND0346 # 12 Y:2000 | 12 | 2000 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $1,827 | $320 | Implemented |
ND0346 # 14 Y:2000 | 14 | 2000 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $64 | $10 | Implemented |
ND0346 # 05 Y:2000 | 05 | 2000 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $12,004 | $50 | Implemented |
ND0346 # 04 Y:2000 | 04 | 2000 | CHECK FOR ACCURACY OF UTILITY / POWER METERS | $25,612 | $500 | Implemented |
UD0593 # 04 Y:2000 | 04 | 2000 | INSTALL / REPAIR INSULATION ON STEAM LINES | $3,243 | $6,080 | Implemented |
UD0593 # 02 Y:2000 | 02 | 2000 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $42,268 | $45,000 | Implemented |