IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

37

matching recommendations
Reset
SIC 3325 Steel Foundries, Nec
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
UD0968 # 17 Y:2017 17 2017 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $27,353 $42,400 Implemented
UD0968 # 05 Y:2017 05 2017 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,870 $0 Implemented
UD0968 # 04 Y:2017 04 2017 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $4,217 $118 Implemented
UD0968 # 03 Y:2017 03 2017 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $3,341 $0 Implemented
UD0968 # 13 Y:2017 13 2017 USE OPTIMUM TEMPERATURE $4,293 $0 Implemented
UD0968 # 16 Y:2017 16 2017 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $37,850 $38,175 Implemented
UD0878 # 06 Y:2013 06 2013 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $16,575 $15,000 Implemented
UD0878 # 02 Y:2013 02 2013 UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT $5,314 $9,180 Implemented
UD0878 # 01 Y:2013 01 2013 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $8,520 $0 Implemented
UD0878 # 05 Y:2013 05 2013 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $6,303 $1,000 Implemented
UD0861 # 10 Y:2012 10 2012 COVER OPEN TANKS $6,786 $0 Implemented
UD0861 # 09 Y:2012 09 2012 COVER OPEN TANKS $6,896 $0 Implemented
UD0861 # 08 Y:2012 08 2012 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $701 $1,000 Implemented
UD0861 # 07 Y:2012 07 2012 UPGRADE CONTROLS ON COMPRESSORS $14,934 $2,000 Implemented
UD0861 # 06 Y:2012 06 2012 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $1,167 $0 Implemented
UD0861 # 13 Y:2012 13 2012 COVER OPEN TANKS $4,954 $0 Implemented
UD0861 # 05 Y:2012 05 2012 DEVELOP A REPAIR/REPLACE POLICY $1,371 $3,440 Implemented
UD0861 # 04 Y:2012 04 2012 TURN OFF EQUIPMENT WHEN NOT IN USE $3,025 $0 Implemented
UD0861 # 01 Y:2012 01 2012 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $15,708 $0 Implemented
UD0861 # 15 Y:2012 15 2012 ISOLATE HOT OR COLD EQUIPMENT $1,382 $1,500 Implemented
UD0749 # 13 Y:2006 13 2006 USE MINIMUM SAFE OVEN VENTILATION $4,400 $0 Implemented
UD0749 # 10 Y:2006 10 2006 INSTALL TIMERS AND/OR THERMOSTATS $22,598 $20,000 Implemented
UD0749 # 09 Y:2006 09 2006 UPGRADE CONTROLS ON COMPRESSORS $25,009 $45,000 Implemented
UD0749 # 08 Y:2006 08 2006 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $98,501 $34,560 Implemented
UD0749 # 05 Y:2006 05 2006 INSULATE BARE EQUIPMENT $128,436 $44,181 Implemented