IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

2,036

matching recommendations
Reset
SIC 335 Nonferrous Rolling And Drawing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
LE0272 # 07 Y:2008 07 2008 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $22,150 $92,543 Not Implemented
LE0271 # 01 Y:2008 01 2008 REPLACE DC EQUIPMENT WITH AC EQUIPMENT $94,198 $45,000 Implemented
LE0271 # 02 Y:2008 02 2008 INSTALL TIMERS AND/OR THERMOSTATS $35,042 $875 Not Implemented
LE0271 # 03 Y:2008 03 2008 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $27,263 $40,000 Not Implemented
LE0271 # 04 Y:2008 04 2008 USE RADIANT HEATER FOR SPOT HEATING $17,604 $3,900 Not Implemented
LE0271 # 05 Y:2008 05 2008 PREHEAT COMBUSTION AIR WITH WASTE HEAT $14,909 $30,000 Not Implemented
LE0271 # 06 Y:2008 06 2008 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $13,337 $3,000 Implemented
LE0271 # 07 Y:2008 07 2008 RECOVER WASTE HEAT FROM EQUIPMENT $6,931 $1,000 Not Implemented
LE0271 # 08 Y:2008 08 2008 REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC $5,095 $7,278 Not Implemented
LE0271 # 09 Y:2008 09 2008 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $2,934 $1,000 Implemented
LE0271 # 10 Y:2008 10 2008 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,865 $150 Not Implemented
LE0271 # 11 Y:2008 11 2008 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $804 $500 Not Implemented
LE0271 # 12 Y:2008 12 2008 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS $704 $255 Not Implemented
LE0271 # 13 Y:2008 13 2008 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $13,736 $54,562 Not Implemented
GT0848 # 01 Y:2008 01 2008 RECOVER WASTE HEAT FROM EQUIPMENT $11,250 $19,500 Not Implemented
GT0848 # 02 Y:2008 02 2008 REPLACE HEAT TREATING OVEN WITH MORE EFFICIENT UNIT $180,800 $541,073 Not Implemented
GT0848 # 03 Y:2008 03 2008 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $340 $1,000 Implemented
GT0848 # 04 Y:2008 04 2008 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,718 $3,250 Implemented
GT0848 # 05 Y:2008 05 2008 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $2,088 $0 Implemented
GT0848 # 06 Y:2008 06 2008 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $4,164 $10,000 Not Implemented
MA0630 # 01 Y:2008 01 2008 USE OUTSIDE COLD WATER SOURCE AS A SUPPLY OF COOLING WATER $29,594 $49,500 Not Implemented
MA0630 # 02 Y:2008 02 2008 USE EXISTING DAM TO GENERATE ELECTRICITY $22,703 $72,000 Not Implemented
MA0630 # 03 Y:2008 03 2008 UTILIZE A LESS EXPENSIVE COOLING METHOD $1,565 $2,000 Implemented
MA0630 # 04 Y:2008 04 2008 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $639 $300 Implemented
MA0630 # 05 Y:2008 05 2008 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $407 $1,944 Not Implemented