Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
261
matching recommendationsSIC | 3351 | Copper Rolling And Drawing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UM0163 # 09 Y:2000 | 09 | 2000 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $56,997 | $90,000 | Implemented |
GT0668 # 01 Y:1999 | 01 | 1999 | ESTABLISH BURNER MAINTENANCE SCHEDULE FOR BOILERS | $3,706 | $0 | Implemented |
GT0668 # 02 Y:1999 | 02 | 1999 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,660 | $1,150 | Not Implemented |
GT0668 # 03 Y:1999 | 03 | 1999 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $23,271 | $27,500 | Not Implemented |
GT0668 # 04 Y:1999 | 04 | 1999 | INSTALL TIMERS AND/OR THERMOSTATS | $678 | $1,000 | Implemented |
GT0668 # 05 Y:1999 | 05 | 1999 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $1,662 | $345 | Implemented |
GT0668 # 06 Y:1999 | 06 | 1999 | REMOVE SLUDGE FROM TANKS ON A REGULAR BASIS | $48,977 | $25,000 | Not Implemented |
GT0668 # 07 Y:1999 | 07 | 1999 | PURCHASE HIGH MATERIALS IN RETURNABLE BULK CONTAINERS | $12,000 | $5,000 | Not Implemented |
GT0668 # 08 Y:1999 | 08 | 1999 | DEVELOP STANDARD OPERATING PROCEDURES | $1,449,000 | $234,000 | Implemented |
MS0059 # 01 Y:1996 | 01 | 1996 | RECOVER WASTE HEAT FROM EQUIPMENT | $6,983 | $2,422 | Not Implemented |
MS0059 # 02 Y:1996 | 02 | 1996 | ADJUST BURNERS FOR EFFICIENT OPERATION | $26,347 | $1,000 | Implemented |
MS0059 # 03 Y:1996 | 03 | 1996 | OPTIMIZE PLANT POWER FACTOR | $9,183 | $18,000 | Not Implemented |
MS0059 # 04 Y:1996 | 04 | 1996 | INSTALL TIMERS AND/OR THERMOSTATS | $1,807 | $1,160 | Not Implemented |
MS0059 # 05 Y:1996 | 05 | 1996 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $35,986 | $23,018 | Not Implemented |
MS0059 # 06 Y:1996 | 06 | 1996 | USE LESS TOXIC AND VOLATILE SOLVENT SUBSTITUTES | $88,560 | $0 | Not Implemented |
UM0037 # 01 Y:1995 | 01 | 1995 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,806 | $4,008 | Not Implemented |
UM0037 # 02 Y:1995 | 02 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $771 | $2,786 | Implemented |
UM0037 # 03 Y:1995 | 03 | 1995 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $286 | $1,200 | Not Implemented |
UM0037 # 04 Y:1995 | 04 | 1995 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT INCOMING FLUIDS | $236 | $300 | Not Implemented |
MA0322 # 01 Y:1995 | 01 | 1995 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $62,376 | $150,000 | Not Implemented |
MA0322 # 02 Y:1995 | 02 | 1995 | TURN OFF EQUIPMENT WHEN NOT IN USE | $20,120 | $1,500 | Implemented |
MA0322 # 03 Y:1995 | 03 | 1995 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $6,158 | $2,200 | Implemented |
MA0322 # 04 Y:1995 | 04 | 1995 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $6,082 | $17,946 | Implemented |
MA0322 # 05 Y:1995 | 05 | 1995 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $2,750 | $500 | Not Implemented |
MA0322 # 06 Y:1995 | 06 | 1995 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $684 | $578 | Not Implemented |