Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
318
matching recommendationsSIC | 3354 | Aluminum Extruded Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UF0302 # 05 Y:2002 | 05 | 2002 | INSTALL / REPAIR INSULATION ON STEAM LINES | $2,883 | $2,330 | Implemented |
UF0302 # 07 Y:2002 | 07 | 2002 | DO NOT USE COMPRESSED AIR FOR PERSONAL COOLING | $4,587 | $0 | Implemented |
MI0033 # 03 Y:2002 | 03 | 2002 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,230 | $117 | Implemented |
MI0026 # 02 Y:2002 | 02 | 2002 | CONDENSE OPERATION INTO ONE BUILDING | $23,625 | $714 | Implemented |
MI0026 # 03 Y:2002 | 03 | 2002 | OPTIMIZE LOT SIZES TO REDUCE INVENTORY CARRYING COSTS | $16,250 | $60 | Implemented |
MI0026 # 04 Y:2002 | 04 | 2002 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,497 | $60 | Implemented |
MI0026 # 05 Y:2002 | 05 | 2002 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $160 | $2 | Implemented |
AS0314 # 01 Y:2001 | 01 | 2001 | INSTALL SKYLIGHTS | $474 | $996 | Implemented |
AS0314 # 02 Y:2001 | 02 | 2001 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $256 | $751 | Implemented |
AS0314 # 03 Y:2001 | 03 | 2001 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $9,375 | $112 | Implemented |
AS0314 # 04 Y:2001 | 04 | 2001 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $538 | $30 | Implemented |
AS0314 # 06 Y:2001 | 06 | 2001 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $142 | $50 | Implemented |
AS0314 # 07 Y:2001 | 07 | 2001 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $11,340 | $1,262 | Implemented |
AS0314 # 08 Y:2001 | 08 | 2001 | RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS | $1,055 | $40 | Implemented |
AS0314 # 09 Y:2001 | 09 | 2001 | CLEAR AND RENT EXISTING SPACE | $38,822 | $4,156 | Implemented |
UU0010 # 01 Y:2001 | 01 | 2001 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $10,308 | $9,973 | Implemented |
UU0010 # 02 Y:2001 | 02 | 2001 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,643 | $75 | Implemented |
UU0010 # 03 Y:2001 | 03 | 2001 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,495 | $680 | Implemented |
UU0010 # 05 Y:2001 | 05 | 2001 | USE SYNTHETIC LUBRICANT | $761 | $600 | Implemented |
WV0226 # 12 Y:2001 | 12 | 2001 | ADVERTISE PRODUCT OR SERVICE | $312,500 | $2,000 | Implemented |
WV0226 # 10 Y:2001 | 10 | 2001 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $7,863 | $1,200 | Implemented |
WV0226 # 08 Y:2001 | 08 | 2001 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $5,542 | $100 | Implemented |
WV0226 # 04 Y:2001 | 04 | 2001 | INSULATE BARE EQUIPMENT | $2,882 | $336 | Implemented |
WV0226 # 03 Y:2001 | 03 | 2001 | INSULATE BARE EQUIPMENT | $4,794 | $1,008 | Implemented |
WV0226 # 02 Y:2001 | 02 | 2001 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $5,673 | $1,100 | Implemented |