Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
768
matching recommendationsSIC | 3354 | Aluminum Extruded Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
ND0361 # 05 Y:2000 | 05 | 2000 | DEVELOP A REPAIR/REPLACE POLICY | $4,112 | $41,893 | Implemented |
ND0361 # 06 Y:2000 | 06 | 2000 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,329 | $400 | Implemented |
OD0167 # 01 Y:2000 | 01 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,906 | $70,918 | n/a |
OD0167 # 02 Y:2000 | 02 | 2000 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,930 | $520 | n/a |
SD0256 # 01 Y:2000 | 01 | 2000 | INSTALL SKYLIGHTS | $18,038 | $27,000 | Implemented |
SD0256 # 02 Y:2000 | 02 | 2000 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $4,703 | $7,230 | Implemented |
SD0256 # 03 Y:2000 | 03 | 2000 | RECOVER WASTE HEAT FROM EQUIPMENT | $205,696 | $64,500 | Not Implemented |
SD0256 # 04 Y:2000 | 04 | 2000 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $2,732 | $5,400 | Not Implemented |
SD0256 # 05 Y:2000 | 05 | 2000 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $290,738 | $0 | Implemented |
GT0681 # 01 Y:1999 | 01 | 1999 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $10,162 | $0 | Not Implemented |
GT0681 # 02 Y:1999 | 02 | 1999 | ADJUST BURNERS FOR EFFICIENT OPERATION | $45,788 | $0 | Not Implemented |
GT0681 # 03 Y:1999 | 03 | 1999 | TREAT AND REUSE EQUIPMENT CLEANING SOLUTIONS | $6,800 | $0 | Not Implemented |
GT0681 # 04 Y:1999 | 04 | 1999 | USE COUNTER CURRENT RINSING TO REDUCE WASTE WATER | $1,667 | $600 | Not Implemented |
GT0681 # 05 Y:1999 | 05 | 1999 | USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL | $12,917 | $4,800 | Implemented |
GT0681 # 06 Y:1999 | 06 | 1999 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $8,596 | $2,360 | Not Implemented |
GT0681 # 07 Y:1999 | 07 | 1999 | TURN OFF EQUIPMENT WHEN NOT IN USE | $1,970 | $1,950 | Not Implemented |
GT0681 # 08 Y:1999 | 08 | 1999 | LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER | $5,540 | $6,700 | Not Implemented |
GT0681 # 09 Y:1999 | 09 | 1999 | USE LESS WASTEFUL PACKAGING | $1,024 | $3,500 | Not Implemented |
GT0681 # 10 Y:1999 | 10 | 1999 | DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS | $125,800 | $64,000 | Not Implemented |
GT0681 # 11 Y:1999 | 11 | 1999 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $4,431 | $57,365 | Not Implemented |
GT0681 # 12 Y:1999 | 12 | 1999 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,768 | $6,225 | Not Implemented |
UF0233 # 01 Y:1999 | 01 | 1999 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,146 | $20,484 | Not Implemented |
UF0233 # 02 Y:1999 | 02 | 1999 | INSTALL ADEQUATE DRYERS ON AIR LINES TO ELIMINATE BLOWDOWN | $1,008 | $750 | Implemented |
UF0233 # 03 Y:1999 | 03 | 1999 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,649 | $320 | Implemented |
UF0233 # 04 Y:1999 | 04 | 1999 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $7,433 | $3,905 | Not Implemented |