IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

2,412

matching recommendations
Reset
SIC 336 Nonferrous Foundries (castings)
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
SD0262 # 06 Y:2001 06 2001 INSULATE BARE EQUIPMENT $12,581 $5,200 Not Implemented
SD0262 # 07 Y:2001 07 2001 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT $24,738 $40,000 Not Implemented
SD0262 # 08 Y:2001 08 2001 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS $5,300 $7,900 Not Implemented
SD0262 # 09 Y:2001 09 2001 INSTALL EQUIPMENT TO MOVE PRODUCT $22,032 $4,304 Not Implemented
SD0262 # 10 Y:2001 10 2001 MODIFY PROCESS TO REDUCE MATERIAL USE/COST $13,222 $4,800 Not Implemented
SD0262 # 11 Y:2001 11 2001 INSTALL CONTINUOUS LUBRICATION EQUIPMENT $47,470 $72,000 Not Implemented
MO0292 # 01 Y:2000 01 2000 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,121 $2,933 Implemented
MO0292 # 02 Y:2000 02 2000 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $6,365 $11,960 Implemented
MO0292 # 03 Y:2000 03 2000 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $3,842 $339 Implemented
MO0292 # 04 Y:2000 04 2000 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $5,013 $80 Implemented
MO0292 # 05 Y:2000 05 2000 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $350 $0 Implemented
MO0292 # 06 Y:2000 06 2000 CONTRACT A WOOD PALLET RECYCLING COMPANY $800 $0 Implemented
MO0292 # 07 Y:2000 07 2000 ELIMINATE SHIFT $1,400,000 $2,000,000 Not Implemented
MO0292 # 08 Y:2000 08 2000 INSTALL SHELVES / RACKS TO UTILIZE UNUSED SPACE $6,804 $500 Not Implemented
OD0166 # 01 Y:2000 01 2000 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,013 $8,525 n/a
OD0166 # 02 Y:2000 02 2000 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,297 $520 n/a
OD0166 # 03 Y:2000 03 2000 ADJUST / MAINTAIN FORK LIFT TRUCKS FOR MOST EFFICIENT OPERATION $13,669 $113,000 n/a
OD0166 # 04 Y:2000 04 2000 METER WASTE WATER $20,038 $6,955 n/a
UM0175 # 01 Y:2000 01 2000 INSTALL OCCUPANCY SENSORS $455 $1,000 Not Implemented
UM0175 # 02 Y:2000 02 2000 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $4,249 $600 Implemented
UM0175 # 03 Y:2000 03 2000 USE "HEAT WHEEL" OR OTHER HEAT EXCHANGER TO CROSS-EXCHANGE BUILDING EXHAUST AIR WITH MAKE-UP AIR $4,332 $6,000 Not Implemented
SD0260 # 01 Y:2000 01 2000 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT $23,150 $30,000 Not Implemented
SD0260 # 02 Y:2000 02 2000 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $10,624 $8,000 Not Implemented
SD0260 # 03 Y:2000 03 2000 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $4,341 $1,326 Not Implemented
SD0260 # 04 Y:2000 04 2000 UTILIZE A LESS EXPENSIVE COOLING METHOD $1,824 $1,500 Not Implemented