Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
20,208
matching recommendationsSIC | 34 | Fabricated Metal Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AM0888 # 11 Y:2023 | 11 | 2023 | INSTALL OCCUPANCY SENSORS | $235 | $550 | Implemented |
TT0300 # 01 Y:2023 | 01 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $46,047 | $221,715 | n/a |
TT0300 # 02 Y:2023 | 02 | 2023 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $41,095 | $32,000 | n/a |
TT0300 # 03 Y:2023 | 03 | 2023 | OPTIMIZE PLANT POWER FACTOR | $22,385 | $37,500 | n/a |
TT0300 # 04 Y:2023 | 04 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $20,075 | $30,000 | n/a |
TT0300 # 05 Y:2023 | 05 | 2023 | RECOVER WASTE HEAT FROM EQUIPMENT | $18,281 | $13,000 | n/a |
TT0300 # 06 Y:2023 | 06 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $14,078 | $18,500 | n/a |
TT0300 # 07 Y:2023 | 07 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $12,049 | $13,500 | n/a |
TT0300 # 08 Y:2023 | 08 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $10,614 | $19,910 | n/a |
TT0300 # 09 Y:2023 | 09 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $8,809 | $156 | n/a |
TT0300 # 10 Y:2023 | 10 | 2023 | UPGRADE CONTROLS ON COMPRESSORS | $8,509 | $17,500 | n/a |
TT0300 # 11 Y:2023 | 11 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,868 | $1,965 | n/a |
SF0607 # 01 Y:2023 | 01 | 2023 | TURN OFF EQUIPMENT WHEN NOT IN USE | $6,168 | $0 | Implemented |
SF0607 # 02 Y:2023 | 02 | 2023 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $3,963 | $344 | Implemented |
SF0607 # 03 Y:2023 | 03 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $16,399 | $8,086 | Implemented |
SF0607 # 04 Y:2023 | 04 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $8,524 | $11,610 | Implemented |
SF0607 # 05 Y:2023 | 05 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $4,254 | $13,352 | Not Implemented |
SF0607 # 06 Y:2023 | 06 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,111 | $9,578 | Not Implemented |
SF0607 # 07 Y:2023 | 07 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $41,060 | $346,427 | Implemented |
UC2310 # 01 Y:2023 | 01 | 2023 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $4,838 | $0 | Implemented |
UC2310 # 02 Y:2023 | 02 | 2023 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $6,116 | $0 | Implemented |
UC2310 # 03 Y:2023 | 03 | 2023 | PAY UTILITY BILLS ON TIME | $146 | $0 | Implemented |
UC2310 # 04 Y:2023 | 04 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $39,506 | $192,621 | Not Implemented |
UC2310 # 05 Y:2023 | 05 | 2023 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $6,045 | $40,103 | Implemented |
UC2310 # 06 Y:2023 | 06 | 2023 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,547 | $1,283 | Implemented |