IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

1,620

matching recommendations
Reset
SIC 34 Fabricated Metal Products
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
UD0770 # 05 Y:2007 05 2007 OPTIMIZE PLANT POWER FACTOR $14,976 $120,000 Not Implemented
UD0770 # 06 Y:2007 06 2007 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $11,018 $40,083 Not Implemented
UD0770 # 07 Y:2007 07 2007 INSTALL SKYLIGHTS $8,153 $30,000 Implemented
UD0770 # 08 Y:2007 08 2007 DEVELOP A REPAIR/REPLACE POLICY $7,672 $42,117 Implemented
UD0770 # 09 Y:2007 09 2007 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,139 $300 Implemented
UD0770 # 10 Y:2007 10 2007 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES $2,532 $0 Implemented
UD0770 # 11 Y:2007 11 2007 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $448 $5,050 Implemented
UM0308 # 01 Y:2006 01 2006 ADJUST BURNERS FOR EFFICIENT OPERATION $3,769 $500 Implemented
UM0308 # 02 Y:2006 02 2006 REDUCE VENTILATION AIR $2,507 $500 Implemented
UM0308 # 03 Y:2006 03 2006 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $2,070 $1,250 Not Implemented
UM0308 # 04 Y:2006 04 2006 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,462 $3,479 Not Implemented
UM0308 # 05 Y:2006 05 2006 RE-SIZE CHARGING OPENINGS OR ADD MOVABLE COVER OR DOOR $536 $300 Implemented
UM0308 # 06 Y:2006 06 2006 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $392 $1,000 Implemented
UM0308 # 07 Y:2006 07 2006 INSULATE BARE EQUIPMENT $142 $310 Not Implemented
UD0746 # 01 Y:2006 01 2006 USE INSULATION IN FURNACES TO FACILITATE HEATING / COOLING $26,993 $2,000 Not Implemented
UD0746 # 02 Y:2006 02 2006 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $20,324 $10,000 Implemented
UD0746 # 03 Y:2006 03 2006 INSULATE BARE EQUIPMENT $19,239 $7,105 Implemented
UD0746 # 04 Y:2006 04 2006 USE HEAT IN FLUE GASES TO PREHEAT PRODUCTS OR MATERIALS $6,408 $0 Implemented
UD0746 # 05 Y:2006 05 2006 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,123 $1,530 Implemented
UD0746 # 06 Y:2006 06 2006 INSTALL OCCUPANCY SENSORS $372 $212 Not Implemented
UM0301 # 01 Y:2006 01 2006 INSULATE BARE EQUIPMENT $9,958 $30,000 Not Implemented
UM0301 # 02 Y:2006 02 2006 INSULATE BARE EQUIPMENT $6,754 $1,971 Implemented
UM0301 # 03 Y:2006 03 2006 INSTALL / REPAIR INSULATION ON STEAM LINES $6,429 $9,875 Not Implemented
UM0301 # 04 Y:2006 04 2006 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $6,344 $500 Not Implemented
UM0301 # 05 Y:2006 05 2006 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $7,457 $375 Implemented