Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,436
matching recommendationsSIC | 34 | Fabricated Metal Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SD0302 # 02 Y:2002 | 02 | 2002 | INSTALL SKYLIGHTS | $6,262 | $2,000 | Not Implemented |
SD0302 # 03 Y:2002 | 03 | 2002 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $6,968 | $12,000 | Not Implemented |
SD0302 # 04 Y:2002 | 04 | 2002 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,228 | $0 | Not Implemented |
SD0302 # 05 Y:2002 | 05 | 2002 | INSTALL OCCUPANCY SENSORS | $964 | $800 | Not Implemented |
SD0302 # 06 Y:2002 | 06 | 2002 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $5,000 | $10,000 | Not Implemented |
SD0302 # 07 Y:2002 | 07 | 2002 | USE DISTILLATION, EVAPORATION TO REMOVE CONTAMINANTS | $5,210 | $6,000 | Not Implemented |
SD0302 # 08 Y:2002 | 08 | 2002 | PAY UTILITY BILLS ON TIME | $427 | $0 | Implemented |
LM0040 # 01 Y:2002 | 01 | 2002 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,685 | $450 | Not Implemented |
LM0040 # 02 Y:2002 | 02 | 2002 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,048 | $600 | Not Implemented |
LM0040 # 03 Y:2002 | 03 | 2002 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,476 | $288 | Implemented |
LM0040 # 04 Y:2002 | 04 | 2002 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $2,360 | $1,440 | Not Implemented |
LM0040 # 05 Y:2002 | 05 | 2002 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $4,888 | $9,000 | Not Implemented |
LM0040 # 06 Y:2002 | 06 | 2002 | MAINTAIN CLEAN CONDITIONS BEFORE PAINTING | $108,300 | $200 | Not Implemented |
LM0040 # 07 Y:2002 | 07 | 2002 | PURCHASE NEW EQUIPMENT TO REDUCE MATERIAL USE / COST | $45,250 | $1,332 | Not Implemented |
LM0040 # 08 Y:2002 | 08 | 2002 | RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS | $13,000 | $3,900 | Not Implemented |
LM0039 # 01 Y:2002 | 01 | 2002 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,575 | $2,880 | Not Implemented |
LM0039 # 02 Y:2002 | 02 | 2002 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,338 | $550 | Not Implemented |
LM0039 # 03 Y:2002 | 03 | 2002 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $211 | $228 | Not Implemented |
LM0039 # 04 Y:2002 | 04 | 2002 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,154 | $0 | Not Implemented |
LM0039 # 05 Y:2002 | 05 | 2002 | RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS | $2,496 | $900 | Not Implemented |
LM0039 # 06 Y:2002 | 06 | 2002 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $20,000 | $600 | Implemented |
LM0039 # 07 Y:2002 | 07 | 2002 | MODIFY STARTUP/SHUTDOWN TIMES | $10,263 | $300 | Not Implemented |
SD0293 # 01 Y:2002 | 01 | 2002 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $42,804 | $52,000 | Implemented |
SD0293 # 02 Y:2002 | 02 | 2002 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $4,322 | $3,700 | Implemented |
SD0293 # 03 Y:2002 | 03 | 2002 | INSTALL OCCUPANCY SENSORS | $5,121 | $1,000 | Implemented |