Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
130
matching recommendationsSIC | 344 | Fabricated Structural Metal Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IP0013 # 03 Y:2013 | 03 | 2013 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $907 | $0 | Not Implemented |
IP0013 # 01 Y:2013 | 01 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $14,266 | $0 | Implemented |
IP0013 # 09 Y:2013 | 09 | 2013 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $1,354 | $2,340 | Implemented |
IP0013 # 08 Y:2013 | 08 | 2013 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $633 | $1,535 | Not Implemented |
IP0013 # 07 Y:2013 | 07 | 2013 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $3,251 | $4,863 | Not Implemented |
IP0013 # 06 Y:2013 | 06 | 2013 | INSTALL OCCUPANCY SENSORS | $4,447 | $2,744 | Implemented |
IP0013 # 05 Y:2013 | 05 | 2013 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $4,079 | $1,148 | Not Implemented |
IP0013 # 04 Y:2013 | 04 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $192 | $0 | Implemented |
IP0013 # 02 Y:2013 | 02 | 2013 | APPLY FOR INVESTMENT INCENTIVES | $4,197 | $0 | Not Implemented |
IP0013 # 10 Y:2013 | 10 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,491 | $15,502 | Implemented |
IP0002 # 08 Y:2012 | 08 | 2012 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $760 | $1,216 | Not Implemented |
IP0002 # 01 Y:2012 | 01 | 2012 | TURN OFF EQUIPMENT WHEN NOT IN USE | $18,621 | $0 | Implemented |
IP0002 # 02 Y:2012 | 02 | 2012 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,887 | $0 | Not Implemented |
IP0002 # 03 Y:2012 | 03 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,515 | $140 | Implemented |
IP0002 # 04 Y:2012 | 04 | 2012 | RECOVER WASTE HEAT FROM EQUIPMENT | $3,900 | $1,320 | Implemented |
IP0002 # 05 Y:2012 | 05 | 2012 | INSTALL DIRECT ACTING UNITS IN PLACE OF COMPRESSED AIR PRESSURE SYSTEM IN SAFETY SYSTEM | $2,700 | $1,250 | Not Implemented |
IP0002 # 06 Y:2012 | 06 | 2012 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $5,124 | $4,678 | Implemented |
IP0002 # 07 Y:2012 | 07 | 2012 | INSULATE BARE EQUIPMENT | $1,205 | $1,430 | Not Implemented |
IC0098 # 02 Y:2005 | 02 | 2005 | REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT | $5,945 | $13,700 | Implemented |
IC0098 # 06 Y:2005 | 06 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $18,283 | $6,200 | Not Implemented |
IC0098 # 05 Y:2005 | 05 | 2005 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,517 | $0 | Not Implemented |
IC0098 # 04 Y:2005 | 04 | 2005 | ELIMINATE LEAKS IN COMBUSTIBLE GAS LINES | $14,532 | $1,400 | Not Implemented |
IC0098 # 03 Y:2005 | 03 | 2005 | TURN OFF EQUIPMENT WHEN NOT IN USE | $2,381 | $0 | Implemented |
IC0098 # 01 Y:2005 | 01 | 2005 | USE PROPERLY DESIGNED AND SIZED HVAC EQUIPMENT | $64,389 | $324,232 | Not Implemented |
UM0266 # 01 Y:2004 | 01 | 2004 | USE FLUE GASES TO HEAT PROCESS OR SERVICE WATER | $11,825 | $4,500 | Implemented |