IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

187

matching recommendations
Reset
SIC 344 Fabricated Structural Metal Products
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
CO0493 # 06 Y:2001 06 2001 INSTALL SHELVES / RACKS TO UTILIZE UNUSED SPACE $7,270 $8,240 Not Implemented
CO0487 # 06 Y:2001 06 2001 REMOVE ROLLERS FROM THE MACHINES AND CLEAN IN A CLOSED SOLVENT CLEANER $1,420 $1,150 Not Implemented
CO0487 # 05 Y:2001 05 2001 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $260 $0 Implemented
CO0487 # 04 Y:2001 04 2001 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,350 $60 Not Implemented
CO0487 # 03 Y:2001 03 2001 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,950 $470 Implemented
CO0487 # 02 Y:2001 02 2001 USE DEMAND CONTROLLER OR LOAD SHEDDER $5,240 $18,000 Not Implemented
CO0487 # 01 Y:2001 01 2001 OPTIMIZE PLANT POWER FACTOR $11,370 $13,000 Not Implemented
CO0479 # 06 Y:2000 06 2000 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $179,700 $0 Not Implemented
CO0479 # 05 Y:2000 05 2000 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $390 $60 Not Implemented
CO0479 # 04 Y:2000 04 2000 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $400 $110 Implemented
CO0479 # 03 Y:2000 03 2000 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS $3,180 $12,990 Not Implemented
CO0479 # 02 Y:2000 02 2000 USE DEMAND CONTROLLER OR LOAD SHEDDER $3,190 $2,500 Implemented
CO0479 # 01 Y:2000 01 2000 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,970 $17,900 n/a
CO0474 # 06 Y:2000 06 2000 PURCHASE RE-CONDITIONED MATERIAL INSTEAD OF NEW $2,400 $0 Not Implemented
CO0474 # 05 Y:2000 05 2000 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $329,200 $60,000 Implemented
CO0474 # 04 Y:2000 04 2000 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $70 $0 Implemented
CO0474 # 03 Y:2000 03 2000 RECOVER WASTE HEAT FROM EQUIPMENT $2,060 $2,250 Not Implemented
CO0474 # 02 Y:2000 02 2000 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,680 $560 Implemented
CO0474 # 01 Y:2000 01 2000 USE DEMAND CONTROLLER OR LOAD SHEDDER $8,930 $10,000 Implemented
CO0441 # 08 Y:1999 08 1999 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $360,000 $375,000 Implemented
CO0441 # 01 Y:1999 01 1999 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $2,470 $2,000 Not Implemented
CO0441 # 02 Y:1999 02 1999 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,366 $6,988 Not Implemented
CO0441 # 03 Y:1999 03 1999 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $1,490 $1,160 Not Implemented
CO0441 # 04 Y:1999 04 1999 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,970 $200 Implemented
CO0441 # 06 Y:1999 06 1999 USE FILTRATION, CENTRIFUGING TO REMOVE CONTAMINANTS $590 $1,090 Not Implemented