Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
40
matching recommendationsSIC | 3441 | Fabricated Structural Metal |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
CO0721 # 01 Y:2016 | 01 | 2016 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,340 | $1,500 | Implemented |
CO0639 # 01 Y:2010 | 01 | 2010 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,180 | $340 | Implemented |
CO0474 # 05 Y:2000 | 05 | 2000 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $329,200 | $60,000 | Implemented |
CO0474 # 04 Y:2000 | 04 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $70 | $0 | Implemented |
CO0474 # 02 Y:2000 | 02 | 2000 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,680 | $560 | Implemented |
CO0474 # 01 Y:2000 | 01 | 2000 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $8,930 | $10,000 | Implemented |
CO0373 # 02 Y:1996 | 02 | 1996 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $688 | $2,390 | Implemented |
CO0373 # 03 Y:1996 | 03 | 1996 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $167 | $82 | Implemented |
CO0373 # 05 Y:1996 | 05 | 1996 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $420 | $620 | Implemented |
CO0373 # 06 Y:1996 | 06 | 1996 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $840 | $250 | Implemented |
CO0318 # 09 Y:1994 | 09 | 1994 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $560 | $960 | Implemented |
CO0318 # 08 Y:1994 | 08 | 1994 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $880 | $370 | Implemented |
CO0318 # 05 Y:1994 | 05 | 1994 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,590 | $2,260 | Implemented |
CO0318 # 04 Y:1994 | 04 | 1994 | REMOVE ROLLERS FROM THE MACHINES AND CLEAN IN A CLOSED SOLVENT CLEANER | $2,210 | $1,750 | Implemented |
CO0318 # 02 Y:1994 | 02 | 1994 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $6,830 | $7,860 | Implemented |
CO0243 # 05 Y:1992 | 05 | 1992 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $230 | $590 | Implemented |
CO0243 # 09 Y:1992 | 09 | 1992 | INSULATE BARE EQUIPMENT | $610 | $3,410 | Implemented |
CO0243 # 08 Y:1992 | 08 | 1992 | USE MINIMUM SAFE OVEN VENTILATION | $260 | $680 | Implemented |
CO0243 # 07 Y:1992 | 07 | 1992 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $6,540 | $16,210 | Implemented |
CO0243 # 06 Y:1992 | 06 | 1992 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $2,380 | $5,600 | Implemented |
CO0243 # 04 Y:1992 | 04 | 1992 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $280 | $220 | Implemented |
CO0243 # 03 Y:1992 | 03 | 1992 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,100 | $230 | Implemented |
CO0243 # 02 Y:1992 | 02 | 1992 | CONVERT COMBUSTION EQUIPMENT TO BURN NATURAL GAS | $11,590 | $5,500 | Implemented |
CO0243 # 01 Y:1992 | 01 | 1992 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $1,490 | $250 | Implemented |
CO0178 # 03 Y:1990 | 03 | 1990 | KEEP DOORS AND WINDOWS SHUT WHEN NOT ON USE | $3,650 | $1,100 | Implemented |