Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
84
matching recommendationsSIC | 3444 | Sheet Metalwork |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AS0305 # 07 Y:2001 | 07 | 2001 | RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS | $63,963 | $6,820 | Implemented |
AS0305 # 06 Y:2001 | 06 | 2001 | INITIATE A TOTAL QUALITY MANAGEMENT PROGRAM | $14,000 | $1,360 | Implemented |
AS0305 # 05 Y:2001 | 05 | 2001 | USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL | $4,588 | $110 | Implemented |
AS0305 # 04 Y:2001 | 04 | 2001 | USE SYNTHETIC LUBRICANT | $592 | $277 | Not Implemented |
AS0305 # 03 Y:2001 | 03 | 2001 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $1,492 | $3,850 | Not Implemented |
AS0305 # 02 Y:2001 | 02 | 2001 | INSTALL OCCUPANCY SENSORS | $155 | $225 | Not Implemented |
AS0305 # 01 Y:2001 | 01 | 2001 | INSTALL SKYLIGHTS | $8,175 | $16,112 | Not Implemented |
AS0304 # 05 Y:2001 | 05 | 2001 | RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS | $64,704 | $8,580 | Implemented |
AS0304 # 01 Y:2001 | 01 | 2001 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $895 | $120 | Not Implemented |
AS0304 # 02 Y:2001 | 02 | 2001 | INSTALL SKYLIGHTS | $1,241 | $1,992 | Not Implemented |
AS0304 # 03 Y:2001 | 03 | 2001 | USE INSULATION IN FURNACES TO FACILITATE HEATING / COOLING | $764 | $2,484 | Not Implemented |
AS0304 # 04 Y:2001 | 04 | 2001 | USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY | $5,488 | $648 | Implemented |
AS0304 # 06 Y:2001 | 06 | 2001 | AUTOMATE FINISHING PROCESS | $58,240 | $688 | Not Implemented |
AS0304 # 07 Y:2001 | 07 | 2001 | DEMOLISH OLD BUILDING TO REDUCE TAX AND INSURANCE BILLS | $29,680 | $438 | Not Implemented |
AS0304 # 08 Y:2001 | 08 | 2001 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $19,493 | $294 | Implemented |
AS0304 # 09 Y:2001 | 09 | 2001 | INITIATE A TOTAL QUALITY MANAGEMENT PROGRAM | $16,000 | $3,940 | Implemented |
AS0301 # 01 Y:2001 | 01 | 2001 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,381 | $2,549 | Not Implemented |
AS0301 # 02 Y:2001 | 02 | 2001 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,767 | $5,107 | Not Implemented |
AS0301 # 03 Y:2001 | 03 | 2001 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $388 | $388 | Not Implemented |
AS0301 # 05 Y:2001 | 05 | 2001 | MODIFY STARTUP/SHUTDOWN TIMES | $48,788 | $383 | Not Implemented |
AS0301 # 04 Y:2001 | 04 | 2001 | USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL | $4,032 | $110 | Implemented |
AS0252 # 03 Y:1999 | 03 | 1999 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $4,590 | $12,314 | Not Implemented |
AS0252 # 04 Y:1999 | 04 | 1999 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,570 | $220 | Implemented |
AS0252 # 02 Y:1999 | 02 | 1999 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $17,693 | $59,800 | Not Implemented |
AS0252 # 01 Y:1999 | 01 | 1999 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,350 | $16,625 | Not Implemented |