Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
2,616
matching recommendationsSIC | 346 | Metal Forgings And Stampings |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IA0221 # 07 Y:1999 | 07 | 1999 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $21,965 | $59,400 | Not Implemented |
IA0221 # 08 Y:1999 | 08 | 1999 | RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE HANDLING COSTS | $20,642 | $11,793 | Implemented |
HO0204 # 01 Y:1999 | 01 | 1999 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $10,583 | $16,842 | Implemented |
HO0204 # 02 Y:1999 | 02 | 1999 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $901 | $0 | Implemented |
HO0204 # 03 Y:1999 | 03 | 1999 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $393 | $492 | Not Implemented |
HO0204 # 04 Y:1999 | 04 | 1999 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,928 | $2,000 | Not Implemented |
HO0204 # 05 Y:1999 | 05 | 1999 | INSTALL / REPAIR INSULATION ON STEAM LINES | $1,517 | $1,424 | Not Implemented |
HO0204 # 06 Y:1999 | 06 | 1999 | INSULATE FEEDWATER TANK | $526 | $438 | Implemented |
HO0204 # 07 Y:1999 | 07 | 1999 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $3,911 | $2,450 | Implemented |
HO0204 # 08 Y:1999 | 08 | 1999 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $1,470 | $483 | Not Implemented |
HO0204 # 09 Y:1999 | 09 | 1999 | ELIMINATE SHUTDOWNS OF CONTROLS DUE TO OVERHEATING | $5,342 | $1,760 | Not Implemented |
HO0204 # 10 Y:1999 | 10 | 1999 | MAINTAIN/ENLARGE A STOCK OF SPARE PARTS | $1,125 | $318 | Implemented |
HO0204 # 11 Y:1999 | 11 | 1999 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $600 | $250 | Not Implemented |
HO0204 # 12 Y:1999 | 12 | 1999 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $6,410 | $1,424 | Not Implemented |
HO0204 # 13 Y:1999 | 13 | 1999 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $2,250 | $120 | Implemented |
HO0204 # 14 Y:1999 | 14 | 1999 | MINIMIZE WATER USAGE | $1,129 | $600 | Not Implemented |
MS0133 # 01 Y:1999 | 01 | 1999 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $20,085 | $881 | Implemented |
MS0133 # 02 Y:1999 | 02 | 1999 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,403 | $360 | Not Implemented |
MS0133 # 03 Y:1999 | 03 | 1999 | INSTALL TIMERS AND/OR THERMOSTATS | $534 | $236 | Implemented |
MS0133 # 04 Y:1999 | 04 | 1999 | USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION | $1,791 | $5,795 | Not Implemented |
MS0133 # 05 Y:1999 | 05 | 1999 | BURN WASTE OIL FOR HEAT | $12,299 | $16,435 | Not Implemented |
MS0133 # 06 Y:1999 | 06 | 1999 | $48,956 | $6,286 | Implemented | |
MA0442 # 01 Y:1999 | 01 | 1999 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $186,395 | $900,000 | Not Implemented |
MA0442 # 02 Y:1999 | 02 | 1999 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $73,450 | $125,600 | Not Implemented |
MA0442 # 03 Y:1999 | 03 | 1999 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $19,396 | $38,500 | Implemented |