IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

34

matching recommendations
Reset
SIC 346 Metal Forgings And Stampings
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
WI0066 # 03 Y:1989 03 1989 INSTALL TIMERS AND/OR THERMOSTATS $2,703 $750 Implemented
WI0066 # 07 Y:1989 07 1989 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS $935 $5,000 Not Implemented
WI0066 # 04 Y:1989 04 1989 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES $2,138 $750 Not Implemented
WI0066 # 05 Y:1989 05 1989 PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER $2,710 $0 Implemented
WI0066 # 09 Y:1989 09 1989 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS $415 $2,000 Not Implemented
WI0066 # 11 Y:1989 11 1989 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $197 $500 Implemented
WI0066 # 06 Y:1989 06 1989 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS $1,350 $450 Implemented
WI0066 # 01 Y:1989 01 1989 IMPROVE LUBRICATION PRACTICES $12,199 $0 Not Implemented
WI0066 # 02 Y:1989 02 1989 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $4,836 $0 Not Implemented
WI0066 # 08 Y:1989 08 1989 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $573 $3,346 Implemented
WI0066 # 10 Y:1989 10 1989 INSTALL SET-BACK TIMERS $481 $400 Implemented
UD0299 # 05 Y:1989 05 1989 LOWER LIGHT FIXTURES IN HIGH CEILING AREAS $1,588 $1,720 Implemented
UD0299 # 04 Y:1989 04 1989 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $889 $750 Implemented
UD0299 # 03 Y:1989 03 1989 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $1,667 $750 Implemented
UD0299 # 02 Y:1989 02 1989 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $900 $0 Implemented
UD0299 # 01 Y:1989 01 1989 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT $7,009 $0 Not Implemented
OK0285 # 03 Y:1989 03 1989 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,367 $0 Implemented
OK0285 # 07 Y:1989 07 1989 RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER $4,306 $390 Implemented
OK0285 # 06 Y:1989 06 1989 USE PLANT OWNED TRANSFORMERS OR LEASE TRANSFORMERS $13,643 $31,400 Implemented
OK0285 # 05 Y:1989 05 1989 INSULATE BARE EQUIPMENT $2,244 $1,161 Implemented
OK0285 # 04 Y:1989 04 1989 RECOVER WASTE HEAT FROM EQUIPMENT $7,072 $98 Implemented
OK0285 # 02 Y:1989 02 1989 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $486 $872 Implemented
OK0285 # 01 Y:1989 01 1989 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,402 $3,870 Implemented
KU0275 # 06 Y:1989 06 1989 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,179 $3,864 Implemented
KU0275 # 05 Y:1989 05 1989 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,101 $270 Implemented