IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

587

matching recommendations
Reset
SIC 349 Misc. Fabricated Metal Products
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
AM0256 # 06 Y:1996 06 1996 INSULATE BARE EQUIPMENT $2,050 $270 Implemented
AM0256 # 07 Y:1996 07 1996 REDUCE / ELIMINATE USE OF DISPOSABLE PRODUCT $1,200 $110 Implemented
AM0250 # 01 Y:1995 01 1995 OPTIMIZE PLANT POWER FACTOR $14,700 $22,050 Not Implemented
AM0250 # 02 Y:1995 02 1995 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $6,320 $1,580 Implemented
AM0250 # 03 Y:1995 03 1995 INSTALL SKYLIGHTS $900 $470 Implemented
AM0250 # 04 Y:1995 04 1995 INSTALL TIMERS AND/OR THERMOSTATS $890 $280 Not Implemented
AM0250 # 05 Y:1995 05 1995 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $730 $0 Implemented
AM0250 # 06 Y:1995 06 1995 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $690 $610 Implemented
AM0250 # 07 Y:1995 07 1995 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $510 $320 Implemented
AM0250 # 08 Y:1995 08 1995 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $400 $0 Not Implemented
AM0250 # 09 Y:1995 09 1995 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED $320 $0 Implemented
AM0209 # 01 Y:1994 01 1994 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT $17,000 $27,760 Not Implemented
AM0209 # 02 Y:1994 02 1994 ADJUST BURNERS FOR EFFICIENT OPERATION $1,890 $540 Implemented
AM0209 # 03 Y:1994 03 1994 INSTALL SKYLIGHTS $955 $1,300 Implemented
AM0209 # 04 Y:1994 04 1994 TURN OFF EQUIPMENT WHEN NOT IN USE $437 $280 Implemented
AM0207 # 01 Y:1994 01 1994 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $34,600 $0 n/a
AM0207 # 02 Y:1994 02 1994 CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS $1,090 $600 n/a
AM0207 # 03 Y:1994 03 1994 CHECK FOR ACCURACY OF UTILITY / POWER METERS $6,600 $700 n/a
AM0207 # 04 Y:1994 04 1994 PAY UTILITY BILLS ON TIME $5,400 $0 n/a
AM0207 # 05 Y:1994 05 1994 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $3,990 $4,300 n/a
AM0207 # 06 Y:1994 06 1994 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $2,150 $0 n/a
AM0207 # 07 Y:1994 07 1994 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED $700 $1,220 n/a
AM0207 # 08 Y:1994 08 1994 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $640 $0 n/a
AM0207 # 09 Y:1994 09 1994 RECOVER AND REUSE WASTE MATERIAL $230 $80 n/a
AM0201 # 01 Y:1994 01 1994 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $37,480 $3,520 Implemented