Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
5,115
matching recommendationsSIC | 349 | Misc. Fabricated Metal Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AM0461 # 10 Y:2004 | 10 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,350 | $200 | Implemented |
AM0461 # 11 Y:2004 | 11 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,255 | $360 | Implemented |
AM0461 # 12 Y:2004 | 12 | 2004 | PAY UTILITY BILLS ON TIME | $370 | $0 | Implemented |
AM0461 # 13 Y:2004 | 13 | 2004 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $360 | $27 | Implemented |
WV0286 # 01 Y:2004 | 01 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,216 | $7,012 | Not Implemented |
WV0286 # 02 Y:2004 | 02 | 2004 | OPTIMIZE PLANT POWER FACTOR | $4,469 | $3,580 | Implemented |
WV0286 # 03 Y:2004 | 03 | 2004 | USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE | $2,072 | $360 | Implemented |
WV0286 # 04 Y:2004 | 04 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,971 | $250 | Implemented |
WV0286 # 05 Y:2004 | 05 | 2004 | DIRECT WARMEST AIR TO COMBUSTION INTAKE | $1,455 | $1,770 | Implemented |
WV0286 # 06 Y:2004 | 06 | 2004 | INSULATE BARE EQUIPMENT | $1,353 | $251 | Implemented |
WV0286 # 07 Y:2004 | 07 | 2004 | DEVELOP A REPAIR/REPLACE POLICY | $1,083 | $375 | Not Implemented |
WV0286 # 08 Y:2004 | 08 | 2004 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $993 | $1,000 | Not Implemented |
WV0286 # 09 Y:2004 | 09 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $830 | $0 | Implemented |
WV0286 # 10 Y:2004 | 10 | 2004 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $828 | $283 | Implemented |
WV0286 # 11 Y:2004 | 11 | 2004 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $743 | $1,100 | Implemented |
WV0286 # 12 Y:2004 | 12 | 2004 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $318 | $250 | Implemented |
UM0249 # 01 Y:2004 | 01 | 2004 | MAINTAIN MACHINES TO REDUCE LEAKS | $78,906 | $4,500 | Implemented |
UM0249 # 02 Y:2004 | 02 | 2004 | USE FILTRATION, CENTRIFUGING TO REMOVE CONTAMINANTS | $59,835 | $55,000 | Not Implemented |
UM0249 # 03 Y:2004 | 03 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $20,288 | $20,400 | Implemented |
UM0249 # 04 Y:2004 | 04 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,027 | $8,138 | Implemented |
UM0249 # 05 Y:2004 | 05 | 2004 | OPTIMIZE PLANT POWER FACTOR | $6,174 | $27,270 | Implemented |
UM0249 # 06 Y:2004 | 06 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,436 | $975 | Implemented |
LL0182 # 01 Y:2004 | 01 | 2004 | REPLACE BOILER | $172,411 | $79,000 | Not Implemented |
LL0182 # 02 Y:2004 | 02 | 2004 | USE WASTE HEAT TO PRODUCE STEAM TO DRIVE A STEAM TURBINE-GENERATOR | $54,044 | $325,479 | Not Implemented |
LL0182 # 03 Y:2004 | 03 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $49,248 | $33,150 | Implemented |