Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
153
matching recommendationsSIC | 3499 | Fabricated Metal Products, Nec |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SF0548 # 07 Y:2019 | 07 | 2019 | USE SOLAR HEAT TO MAKE ELECTRICTY | $39,924 | $172,115 | Implemented |
SD0547 # 07 Y:2017 | 07 | 2017 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $689 | $567 | Implemented |
SD0547 # 06 Y:2017 | 06 | 2017 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $725 | $914 | Not Implemented |
SD0547 # 04 Y:2017 | 04 | 2017 | INSTALL OCCUPANCY SENSORS | $1,746 | $2,045 | Not Implemented |
SD0547 # 05 Y:2017 | 05 | 2017 | INSULATE BARE EQUIPMENT | $1,326 | $750 | Implemented |
SD0547 # 02 Y:2017 | 02 | 2017 | USE PHOTOCELL CONTROLS | $3,679 | $11,568 | Implemented |
SD0547 # 03 Y:2017 | 03 | 2017 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,165 | $1,500 | Implemented |
SD0547 # 01 Y:2017 | 01 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,853 | $20,582 | Implemented |
SD0484 # 01 Y:2014 | 01 | 2014 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $111,951 | $87,500 | Not Implemented |
SD0484 # 04 Y:2014 | 04 | 2014 | REDUCE TEMPERATURE OF PROCESS EQUIPMENT WHEN ON STANDBY | $6,896 | $400 | Implemented |
SD0484 # 02 Y:2014 | 02 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $20,136 | $45,100 | Implemented |
SD0484 # 03 Y:2014 | 03 | 2014 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $7,196 | $1,300 | Implemented |
SD0484 # 07 Y:2014 | 07 | 2014 | USE PHOTOCELL CONTROLS | $1,281 | $3,700 | Implemented |
SD0484 # 05 Y:2014 | 05 | 2014 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,758 | $300 | Implemented |
SD0484 # 06 Y:2014 | 06 | 2014 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,388 | $4,600 | Not Implemented |
SD0443 # 04 Y:2012 | 04 | 2012 | USE INSULATION IN FURNACES TO FACILITATE HEATING / COOLING | $1,443 | $618 | Implemented |
SD0443 # 03 Y:2012 | 03 | 2012 | ADD AREA LIGHTING SWITCHES | $420 | $115 | Implemented |
SD0443 # 02 Y:2012 | 02 | 2012 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $7,935 | $2,500 | Implemented |
SD0443 # 05 Y:2012 | 05 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,415 | $800 | Implemented |
SD0443 # 07 Y:2012 | 07 | 2012 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $3,010 | $2,500 | Implemented |
SD0443 # 01 Y:2012 | 01 | 2012 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $591 | $100 | Implemented |
SD0443 # 06 Y:2012 | 06 | 2012 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $3,400 | $2,500 | Implemented |
SD0443 # 09 Y:2012 | 09 | 2012 | INSTALL OCCUPANCY SENSORS | $395 | $989 | Implemented |
SD0443 # 08 Y:2012 | 08 | 2012 | USE PHOTOCELL CONTROLS | $1,660 | $2,700 | Implemented |
SD0404 # 06 Y:2008 | 06 | 2008 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $2,452 | $2,144 | Implemented |