Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
7,093
matching recommendationsSIC | 35 | Industrial Machinery And Equipment |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
CO0260 # 07 Y:1992 | 07 | 1992 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $84,970 | $120,000 | Implemented |
CO0260 # 08 Y:1992 | 08 | 1992 | INSULATE BARE EQUIPMENT | $1,500 | $700 | Implemented |
CO0260 # 09 Y:1992 | 09 | 1992 | REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED | $5,880 | $7,700 | Implemented |
CO0260 # 10 Y:1992 | 10 | 1992 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $300 | $150 | Implemented |
CO0260 # 11 Y:1992 | 11 | 1992 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $106 | $900 | Implemented |
CO0260 # 12 Y:1992 | 12 | 1992 | COOL COMPRESSOR AIR INTAKE WITH HEAT EXCHANGER | $14,750 | $20,280 | Implemented |
CO0260 # 13 Y:1992 | 13 | 1992 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,130 | $2,870 | Implemented |
CO0260 # 14 Y:1992 | 14 | 1992 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $820 | $2,610 | Implemented |
GT0481 # 01 Y:1992 | 01 | 1992 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $2,300 | $900 | Implemented |
GT0481 # 02 Y:1992 | 02 | 1992 | INCREASE AMOUNT OF CONDENSATE RETURNED | $23,265 | $7,500 | Implemented |
GT0481 # 03 Y:1992 | 03 | 1992 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $46,920 | $60,000 | Implemented |
GT0481 # 04 Y:1992 | 04 | 1992 | RECOVER AND REUSE COOLING WATER | $5,790 | $800 | Implemented |
GT0481 # 05 Y:1992 | 05 | 1992 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $498 | $2,540 | Implemented |
GT0481 # 06 Y:1992 | 06 | 1992 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $545 | $0 | Implemented |
GT0481 # 07 Y:1992 | 07 | 1992 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,197 | $7,700 | Implemented |
GT0481 # 08 Y:1992 | 08 | 1992 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $37,700 | $40,240 | Implemented |
GT0481 # 09 Y:1992 | 09 | 1992 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,814 | $22,050 | Implemented |
GT0481 # 10 Y:1992 | 10 | 1992 | USE FOSSIL FUEL POWERED GENERATOR DURING PEAK DEMAND PERIODS | $175,445 | $450,000 | Implemented |
ND0042 # 01 Y:1992 | 01 | 1992 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,027 | $350 | Implemented |
ND0042 # 02 Y:1992 | 02 | 1992 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $759 | $7,880 | Implemented |
ND0042 # 03 Y:1992 | 03 | 1992 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $305 | $10,000 | Implemented |
ND0042 # 04 Y:1992 | 04 | 1992 | USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE | $186 | $436 | Implemented |
ND0042 # 05 Y:1992 | 05 | 1992 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $241 | $88 | Implemented |
ND0046 # 02 Y:1992 | 02 | 1992 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $582 | $4,765 | Implemented |
ND0046 # 04 Y:1992 | 04 | 1992 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $582 | $300 | Implemented |