IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

1,027

matching recommendations
Reset
SIC 35 Industrial Machinery And Equipment
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
AM0735 # 04 Y:2017 04 2017 INSTALL OCCUPANCY SENSORS $920 $1,700 Not Implemented
AM0735 # 05 Y:2017 05 2017 REUSE RAGS UNTIL COMPLETELY SOILED $880 $0 Implemented
AM0735 # 06 Y:2017 06 2017 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,160 $500 Implemented
AM0735 # 07 Y:2017 07 2017 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,105 $410 Implemented
AM0735 # 08 Y:2017 08 2017 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $195 $15 Not Implemented
AM0712 # 01 Y:2016 01 2016 CONVERT TO HIGH VOLUME LOW PRESSURE (HVLP) PAINT GUNS $48,140 $2,710 Not Implemented
AM0712 # 02 Y:2016 02 2016 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $24,510 $46,840 Not Implemented
AM0712 # 03 Y:2016 03 2016 OPTIMIZE PLANT POWER FACTOR $11,700 $26,740 Not Implemented
AM0712 # 04 Y:2016 04 2016 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $2,710 $30 Not Implemented
AM0712 # 05 Y:2016 05 2016 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $450 $200 Not Implemented
AM0712 # 06 Y:2016 06 2016 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED $400 $0 Not Implemented
AM0712 # 07 Y:2016 07 2016 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $350 $150 Not Implemented
AM0712 # 08 Y:2016 08 2016 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL $110 $280 Not Implemented
OK0941 # 01 Y:2016 01 2016 INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT $3,672 $11,835 Not Implemented
OK0941 # 02 Y:2016 02 2016 INSTALL SET-BACK TIMERS $2,732 $245 Not Implemented
OK0941 # 03 Y:2016 03 2016 CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS $1,497 $1,960 Implemented
OK0941 # 04 Y:2016 04 2016 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $7,762 $25,920 Implemented
OK0941 # 05 Y:2016 05 2016 TURN OFF EQUIPMENT WHEN NOT IN USE $454 $0 Not Implemented
OK0941 # 06 Y:2016 06 2016 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $102 $350 Not Implemented
OK0941 # 07 Y:2016 07 2016 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $58 $336 Not Implemented
AM0696 # 01 Y:2015 01 2015 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS $16,880 $30,000 Not Implemented
AM0696 # 02 Y:2015 02 2015 MODIFY WORKLOAD $8,280 $0 Not Implemented
AM0696 # 03 Y:2015 03 2015 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $7,810 $28,220 Implemented
AM0696 # 04 Y:2015 04 2015 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,720 $3,060 Not Implemented
AM0696 # 05 Y:2015 05 2015 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED $870 $0 Implemented