Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
55
matching recommendationsSIC | 355 | Special Industry Machinery |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MI0096 # 01 Y:2004 | 01 | 2004 | TURN OFF EQUIPMENT WHEN NOT IN USE | $6,113 | $800 | Not Implemented |
MI0096 # 07 Y:2004 | 07 | 2004 | COVER OPEN TANKS | $34 | $25 | Implemented |
MI0096 # 06 Y:2004 | 06 | 2004 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $110 | $56 | Implemented |
MI0096 # 04 Y:2004 | 04 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $-147 | $1,015 | Not Implemented |
MI0096 # 03 Y:2004 | 03 | 2004 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $6,619 | $150 | Implemented |
MI0096 # 02 Y:2004 | 02 | 2004 | ESTABLISH A PREVENTATIVE MAINTENANCE PROGRAM | $3,213 | $1,250 | Implemented |
MI0096 # 05 Y:2004 | 05 | 2004 | USE SYNTHETIC LUBRICANT | $696 | $189 | Not Implemented |
LE0201 # 07 Y:2004 | 07 | 2004 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $3,924 | $2,115 | Implemented |
LE0201 # 06 Y:2004 | 06 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $196 | $150 | Not Implemented |
LE0201 # 05 Y:2004 | 05 | 2004 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $551 | $150 | Implemented |
LE0201 # 04 Y:2004 | 04 | 2004 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $1,622 | $450 | Not Implemented |
LE0201 # 03 Y:2004 | 03 | 2004 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $3,356 | $2,500 | Implemented |
LE0201 # 02 Y:2004 | 02 | 2004 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $5,658 | $0 | Not Implemented |
LE0201 # 01 Y:2004 | 01 | 2004 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $7,994 | $0 | Implemented |
IA0347 # 05 Y:2004 | 05 | 2004 | INSTALL OCCUPANCY SENSORS | $1,911 | $1,820 | Implemented |
IA0347 # 09 Y:2004 | 09 | 2004 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $244 | $0 | Implemented |
IA0347 # 08 Y:2004 | 08 | 2004 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $29,440 | $50,000 | Not Implemented |
IA0347 # 07 Y:2004 | 07 | 2004 | TURN OFF EQUIPMENT WHEN NOT IN USE | $3,967 | $148 | Implemented |
IA0347 # 06 Y:2004 | 06 | 2004 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $929 | $457 | Implemented |
IA0347 # 04 Y:2004 | 04 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,608 | $2,591 | Implemented |
IA0347 # 03 Y:2004 | 03 | 2004 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $3,243 | $1,090 | Implemented |
IA0347 # 02 Y:2004 | 02 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,623 | $920 | Implemented |
IA0347 # 01 Y:2004 | 01 | 2004 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,115 | $14 | Not Implemented |
UD0706 # 10 Y:2004 | 10 | 2004 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $42 | $0 | Not Implemented |
TA0082 # 01 Y:2004 | 01 | 2004 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $14,730 | $0 | Implemented |