IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

36

matching recommendations
Reset
SIC 355 Special Industry Machinery
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
UC2317 # 09 Y:2023 09 2023 ADOPT IN-HOUSE MATERIAL GENERATION $30,659 $188,853 Not Implemented
UC2317 # 01 Y:2023 01 2023 OPTIMIZE PLANT POWER FACTOR $90,350 $29,189 Not Implemented
UC2317 # 02 Y:2023 02 2023 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $392 $75 Not Implemented
UC2317 # 03 Y:2023 03 2023 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,123 $428 Not Implemented
UC2317 # 04 Y:2023 04 2023 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,584 $1,300 Not Implemented
UC2317 # 12 Y:2023 12 2023 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE $5,411 $0 Not Implemented
UC2317 # 05 Y:2023 05 2023 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $5,240 $50 Not Implemented
UC2317 # 06 Y:2023 06 2023 CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS $714 $540 Not Implemented
UC2317 # 10 Y:2023 10 2023 INSTALL TIMERS AND/OR THERMOSTATS $6,903 $1,468 Not Implemented
UC2317 # 07 Y:2023 07 2023 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $7,763 $17,190 Not Implemented
UC2317 # 11 Y:2023 11 2023 USE SOLAR HEAT TO MAKE ELECTRICTY $321,413 $2,701,940 Not Implemented
UC2317 # 08 Y:2023 08 2023 RECOVER WASTE HEAT FROM EQUIPMENT $1,409 $34,609 Not Implemented
CM1025 # 03 Y:2023 03 2023 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $6,196 $889 n/a
CM1025 # 04 Y:2023 04 2023 UPGRADE CONTROLS ON COMPRESSORS $2,954 $22,704 n/a
CM1025 # 05 Y:2023 05 2023 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,162 $2,172 n/a
CM1025 # 02 Y:2023 02 2023 CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD $5,141 $28,827 n/a
CM1025 # 01 Y:2023 01 2023 USE SOLAR HEAT TO MAKE ELECTRICTY $34,270 $526,058 n/a
LS2316 # 03 Y:2023 03 2023 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $33,726 $4,515 Implemented
LS2316 # 06 Y:2023 06 2023 INSTALL OCCUPANCY SENSORS $460 $753 Implemented
LS2316 # 05 Y:2023 05 2023 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $47,296 $25,200 Not Implemented
LS2316 # 04 Y:2023 04 2023 USE PHOTOCELL CONTROLS $1,069 $370 Not Implemented
LS2316 # 02 Y:2023 02 2023 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,894 $135 Implemented
LS2316 # 01 Y:2023 01 2023 INSTALL TIMERS AND/OR THERMOSTATS $3,030 $30 Not Implemented
CM1024 # 05 Y:2023 05 2023 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $760 $75 n/a
CM1024 # 02 Y:2023 02 2023 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $5,939 $6,474 n/a