Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
3,257
matching recommendationsSIC | 356 | General Industrial Machinery |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IP0155 # 03 Y:2022 | 03 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,553 | $131 | Implemented |
IP0155 # 04 Y:2022 | 04 | 2022 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $13,401 | $740 | Implemented |
IP0155 # 05 Y:2022 | 05 | 2022 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,705 | $1,518 | Implemented |
IP0155 # 06 Y:2022 | 06 | 2022 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,289 | $1,882 | Implemented |
IP0155 # 07 Y:2022 | 07 | 2022 | USE PHOTOCELL CONTROLS | $152 | $456 | Implemented |
IP0155 # 08 Y:2022 | 08 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $557 | $2,516 | Implemented |
MZ0315 # 01 Y:2022 | 01 | 2022 | USE RADIANT HEATER FOR SPOT HEATING | $15,635 | $15,360 | Not Implemented |
MZ0315 # 02 Y:2022 | 02 | 2022 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $2,404 | $480 | Implemented |
MZ0315 # 03 Y:2022 | 03 | 2022 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $2,771 | $14,420 | Implemented |
MZ0315 # 04 Y:2022 | 04 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,247 | $250 | Implemented |
MZ0315 # 05 Y:2022 | 05 | 2022 | INSTALL OCCUPANCY SENSORS | $3,818 | $360 | Implemented |
MZ0315 # 06 Y:2022 | 06 | 2022 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $16,735 | $15,782 | Implemented |
MZ0315 # 07 Y:2022 | 07 | 2022 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $34,981 | $1,350 | Not Implemented |
MZ0315 # 08 Y:2022 | 08 | 2022 | USE SOLAR HEAT TO MAKE ELECTRICTY | $138,217 | $836,000 | Not Implemented |
MZ0321 # 01 Y:2021 | 01 | 2021 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $14,197 | $657 | Implemented |
MZ0321 # 02 Y:2021 | 02 | 2021 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $21,760 | $11,000 | Implemented |
MZ0321 # 03 Y:2021 | 03 | 2021 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $46,936 | $63,900 | Implemented |
MZ0321 # 04 Y:2021 | 04 | 2021 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $23,778 | $5,120 | Implemented |
MZ0321 # 05 Y:2021 | 05 | 2021 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $33,649 | $58,976 | Not Implemented |
GT0957 # 01 Y:2021 | 01 | 2021 | TURN OFF EQUIPMENT WHEN NOT IN USE | $17,635 | $350 | Implemented |
GT0957 # 02 Y:2021 | 02 | 2021 | AIR CONDITION ONLY SPACE NECESSARY | $4,101 | $200 | Implemented |
GT0957 # 03 Y:2021 | 03 | 2021 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $15,872 | $1,050 | Implemented |
GT0957 # 04 Y:2021 | 04 | 2021 | CHILL WATER TO THE HIGHEST TEMPERATURE POSSIBLE | $1,152 | $250 | Not Implemented |
GT0957 # 05 Y:2021 | 05 | 2021 | INSTALL TIMERS AND/OR THERMOSTATS | $3,211 | $1,067 | Implemented |
GT0957 # 06 Y:2021 | 06 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $53,036 | $38,422 | Implemented |