Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
154
matching recommendationsSIC | 356 | General Industrial Machinery |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
GT0696 # 06 Y:2000 | 06 | 2000 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $100,083 | $160,000 | Not Implemented |
GT0696 # 07 Y:2000 | 07 | 2000 | CONTRACT A WOOD PALLET RECYCLING COMPANY | $7,200 | $0 | Implemented |
GT0696 # 08 Y:2000 | 08 | 2000 | REGRIND, REUSE, OR SELL SCRAP PLASTIC PARTS | $360 | $0 | Implemented |
GT0644 # 01 Y:1998 | 01 | 1998 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $303 | $0 | Implemented |
GT0644 # 02 Y:1998 | 02 | 1998 | COVER OPEN TANKS | $6,346 | $1,838 | Not Implemented |
GT0644 # 03 Y:1998 | 03 | 1998 | TURN OFF EQUIPMENT WHEN NOT IN USE | $6,251 | $0 | Implemented |
GT0644 # 04 Y:1998 | 04 | 1998 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,049 | $5,558 | Not Implemented |
GT0644 # 05 Y:1998 | 05 | 1998 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,160 | $750 | Implemented |
GT0644 # 06 Y:1998 | 06 | 1998 | CONVERT TO HIGH VOLUME LOW PRESSURE (HVLP) PAINT GUNS | $12,300 | $2,000 | Not Implemented |
GT0644 # 07 Y:1998 | 07 | 1998 | UTILIZE A CENTRAL COOLANT SYSTEM FOR CLEANING AND REUSE OF METAL WORKING FLUID | $21,400 | $32,860 | Not Implemented |
GT0644 # 08 Y:1998 | 08 | 1998 | FILTER AND REUSE HYDRAULIC OIL | $7,448 | $4,500 | Not Implemented |
GT0644 # 09 Y:1998 | 09 | 1998 | CONDENSE OPERATION INTO ONE BUILDING | $6,516 | $0 | Implemented |
GT0624 # 01 Y:1997 | 01 | 1997 | LOWER LIGHT FIXTURES IN HIGH CEILING AREAS | $2,995 | $4,380 | Implemented |
GT0624 # 02 Y:1997 | 02 | 1997 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,420 | $900 | Implemented |
GT0624 # 03 Y:1997 | 03 | 1997 | TURN OFF EQUIPMENT WHEN NOT IN USE | $1,480 | $150 | Implemented |
GT0624 # 04 Y:1997 | 04 | 1997 | UPGRADE CONTROLS ON COMPRESSORS | $2,470 | $0 | Not Implemented |
GT0624 # 05 Y:1997 | 05 | 1997 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $80 | $250 | Not Implemented |
GT0624 # 06 Y:1997 | 06 | 1997 | CONVERT TO ELECTROSTATIC POWDER COATING | $6,540 | $0 | Not Implemented |
GT0624 # 07 Y:1997 | 07 | 1997 | REPLACE CITY WATER WITH RECYCLED WATER VIA COOLING TOWER | $1,600 | $1,320 | Not Implemented |
GT0624 # 08 Y:1997 | 08 | 1997 | MODIFY PROCESS TO REDUCE MATERIAL USE/COST | $18,900 | $4,000 | Not Implemented |
GT0576 # 01 Y:1995 | 01 | 1995 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $6,700 | $0 | Not Implemented |
GT0576 # 02 Y:1995 | 02 | 1995 | RECOVER WASTE HEAT FROM EQUIPMENT | $670 | $1,450 | Not Implemented |
GT0576 # 03 Y:1995 | 03 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $510 | $720 | Implemented |
GT0576 # 04 Y:1995 | 04 | 1995 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,840 | $200 | Implemented |
GT0576 # 05 Y:1995 | 05 | 1995 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $20,855 | $66,000 | Not Implemented |