Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
8,385
matching recommendationsSIC | 36 | Electronic & Other Electric Equipment |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MU0036 # 01 Y:2023 | 01 | 2023 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,852 | $0 | n/a |
MU0036 # 02 Y:2023 | 02 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $388 | $0 | n/a |
MU0036 # 03 Y:2023 | 03 | 2023 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $10,129 | $49,885 | n/a |
MU0036 # 04 Y:2023 | 04 | 2023 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $1,737 | $0 | n/a |
MU0036 # 05 Y:2023 | 05 | 2023 | USE PHOTOCELL CONTROLS | $756 | $0 | n/a |
MU0036 # 06 Y:2023 | 06 | 2023 | INSTALL OCCUPANCY SENSORS | $1,296 | $30 | n/a |
MU0036 # 07 Y:2023 | 07 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,370 | $0 | n/a |
MU0036 # 08 Y:2023 | 08 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $305 | $1,240 | n/a |
MU0036 # 09 Y:2023 | 09 | 2023 | INSTALL OR UPGRADE INSULATION ON HVAC DISTRIBUTION SYSTEMS | $3,433 | $3,037 | n/a |
MU0036 # 10 Y:2023 | 10 | 2023 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $902 | $0 | n/a |
MU0036 # 11 Y:2023 | 11 | 2023 | USE RADIANT HEATER FOR SPOT HEATING | $4,730 | $5,760 | n/a |
MU0036 # 12 Y:2023 | 12 | 2023 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $12,544 | $17,271 | n/a |
MU0036 # 13 Y:2023 | 13 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $5,347 | $25,171 | n/a |
IC0284 # 01 Y:2023 | 01 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,480 | $3,669 | n/a |
IC0284 # 02 Y:2023 | 02 | 2023 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $4,864 | $0 | n/a |
IC0284 # 03 Y:2023 | 03 | 2023 | MAINTAIN AIR FILTERS BY CLEANING OR REPLACEMENT | $445 | $0 | n/a |
IC0284 # 04 Y:2023 | 04 | 2023 | INSULATE BARE EQUIPMENT | $556 | $897 | n/a |
IC0284 # 05 Y:2023 | 05 | 2023 | USE DIRECT FLAME IMPINGEMENT OR INFRARED PROCESSING FOR CHAMBER TYPE HEATING | $152,337 | $14,315 | n/a |
IC0284 # 06 Y:2023 | 06 | 2023 | PURCHASE EQUIPMENT INSTEAD OF LEASING | $192,600 | $121,203 | n/a |
IC0284 # 07 Y:2023 | 07 | 2023 | TURN OFF EQUIPMENT WHEN NOT IN USE | $415 | $0 | n/a |
IC0284 # 08 Y:2023 | 08 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $190 | $379 | n/a |
TT0297 # 01 Y:2023 | 01 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $49,703 | $203,650 | n/a |
TT0297 # 02 Y:2023 | 02 | 2023 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $13,890 | $1,250 | n/a |
TT0297 # 03 Y:2023 | 03 | 2023 | INSTALL OCCUPANCY SENSORS | $11,161 | $14,500 | n/a |
TT0297 # 04 Y:2023 | 04 | 2023 | OPTIMIZE PLANT POWER FACTOR | $8,533 | $20,000 | n/a |