Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
4,221
matching recommendationsSIC | 37 | Transportation Equipment |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MZ0264 # 04 Y:2019 | 04 | 2019 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $1,987 | $1,460 | Implemented |
MZ0264 # 07 Y:2019 | 07 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $975 | $836 | Implemented |
MZ0264 # 08 Y:2019 | 08 | 2019 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $420 | $274 | Implemented |
UU0140 # 01 Y:2019 | 01 | 2019 | TURN OFF EQUIPMENT WHEN NOT IN USE | $22,415 | $2,000 | Implemented |
UU0140 # 03 Y:2019 | 03 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,922 | $2,000 | Implemented |
UU0140 # 04 Y:2019 | 04 | 2019 | TURN OFF EQUIPMENT WHEN NOT IN USE | $4,500 | $0 | Implemented |
UU0140 # 06 Y:2019 | 06 | 2019 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $831 | $400 | Implemented |
NL0027 # 01 Y:2018 | 01 | 2018 | REPLACE CITY WATER WITH RECYCLED WATER VIA COOLING TOWER | $24,797 | $32,620 | Implemented |
NL0027 # 02 Y:2018 | 02 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $18,840 | $74,980 | Implemented |
NL0027 # 05 Y:2018 | 05 | 2018 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $326 | $1,000 | Implemented |
TT0212 # 02 Y:2018 | 02 | 2018 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $68,776 | $32,000 | Implemented |
TT0212 # 04 Y:2018 | 04 | 2018 | INSTALL OR UPGRADE INSULATION ON HVAC DISTRIBUTION SYSTEMS | $38,635 | $13,000 | Implemented |
TT0212 # 05 Y:2018 | 05 | 2018 | METER WASTE WATER | $34,128 | $1,900 | Implemented |
TT0212 # 09 Y:2018 | 09 | 2018 | INSTALL MOTOR VOLTAGE CONTROLLER ON LIGHTLY LOADED MOTORS | $3,775 | $5,000 | Implemented |
TT0212 # 11 Y:2018 | 11 | 2018 | INSTALL OCCUPANCY SENSORS | $283 | $250 | Implemented |
NC0622 # 01 Y:2018 | 01 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $13,812 | $46,617 | Implemented |
NC0622 # 02 Y:2018 | 02 | 2018 | INSTALL OCCUPANCY SENSORS | $481 | $250 | Implemented |
NC0622 # 03 Y:2018 | 03 | 2018 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,414 | $525 | Implemented |
NC0622 # 09 Y:2018 | 09 | 2018 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $15,903 | $500 | Implemented |
WM0127 # 05 Y:2018 | 05 | 2018 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $3,828 | $0 | Implemented |
WM0127 # 09 Y:2018 | 09 | 2018 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $2,110 | $0 | Implemented |
WM0127 # 10 Y:2018 | 10 | 2018 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $600 | $1,511 | Implemented |
SU0470 # 08 Y:2018 | 08 | 2018 | INSTALL / REPAIR INSULATION ON STEAM LINES | $436 | $478 | Implemented |
SU0470 # 10 Y:2018 | 10 | 2018 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $622 | $907 | Implemented |
OK0996 # 01 Y:2018 | 01 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $32,265 | $25,906 | Implemented |