Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
188
matching recommendationsSIC | 37 | Transportation Equipment |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK0552 # 04 Y:1998 | 04 | 1998 | INSTALL OCCUPANCY SENSORS | $873 | $651 | Implemented |
OK0552 # 05 Y:1998 | 05 | 1998 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $142 | $54 | Implemented |
OK0552 # 06 Y:1998 | 06 | 1998 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $581 | $375 | Implemented |
OK0552 # 07 Y:1998 | 07 | 1998 | REDUCE EXCESSIVE BOILER BLOWDOWN | $1,324 | $5,000 | Implemented |
OK0552 # 08 Y:1998 | 08 | 1998 | INSULATE BARE EQUIPMENT | $193 | $209 | Implemented |
OK0553 # 01 Y:1998 | 01 | 1998 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $69,793 | $76,000 | Implemented |
OK0553 # 03 Y:1998 | 03 | 1998 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $14,035 | $6,760 | Implemented |
OK0529 # 04 Y:1997 | 04 | 1997 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,030 | $4,595 | Implemented |
OK0529 # 07 Y:1997 | 07 | 1997 | RECOVER WASTE HEAT FROM EQUIPMENT | $499 | $1,086 | Implemented |
OK0529 # 08 Y:1997 | 08 | 1997 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $207 | $1,440 | Implemented |
OK0487 # 02 Y:1996 | 02 | 1996 | RECYCLE AIR FOR HEATING, VENTILATION AND AIR CONDITIONING | $2,235 | $4,100 | Implemented |
OK0487 # 03 Y:1996 | 03 | 1996 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,133 | $1,460 | Implemented |
OK0487 # 05 Y:1996 | 05 | 1996 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $213 | $400 | Implemented |
OK0487 # 06 Y:1996 | 06 | 1996 | REPLACE CITY WATER WITH RECYCLED WATER VIA COOLING TOWER | $11,121 | $2,000 | Implemented |
OK0487 # 07 Y:1996 | 07 | 1996 | BURN WOOD BY-PRODUCTS FOR HEAT | $2,800 | $1,500 | Implemented |
OK0487 # 08 Y:1996 | 08 | 1996 | LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER | $1,650 | $0 | Implemented |
OK0486 # 02 Y:1996 | 02 | 1996 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $5,401 | $3,275 | Implemented |
OK0486 # 04 Y:1996 | 04 | 1996 | UPGRADE CONTROLS ON COMPRESSORS | $1,548 | $5,600 | Implemented |
OK0486 # 05 Y:1996 | 05 | 1996 | DISCONNECT BALLASTS | $428 | $1,060 | Implemented |
OK0486 # 06 Y:1996 | 06 | 1996 | INSTALL / REPAIR INSULATION ON STEAM LINES | $203 | $757 | Implemented |
OK0429 # 01 Y:1994 | 01 | 1994 | LIMIT AND CONTROL SECONDARY COMBUSTION AIR IN FURNACE | $1,839 | $2,500 | Implemented |
OK0429 # 02 Y:1994 | 02 | 1994 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,730 | $1,600 | Implemented |
OK0429 # 03 Y:1994 | 03 | 1994 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,310 | $0 | Implemented |
OK0429 # 04 Y:1994 | 04 | 1994 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $638 | $0 | Implemented |
OK0426 # 01 Y:1994 | 01 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,558 | $3,224 | Implemented |