Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
9,504
matching recommendationsSIC | 37 | Transportation Equipment |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UF0118 # 09 Y:1995 | 09 | 1995 | OPTIMIZE PRODUCTION LOT SIZES AND INVENTORIES | $17,631 | $7,000 | Not Implemented |
ND0209 # 01 Y:1995 | 01 | 1995 | USE RADIANT HEATER FOR SPOT HEATING | $484 | $0 | Not Implemented |
ND0209 # 02 Y:1995 | 02 | 1995 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,079 | $1,200 | Implemented |
ND0209 # 03 Y:1995 | 03 | 1995 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $1,016 | $490 | Implemented |
ND0209 # 04 Y:1995 | 04 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $926 | $547 | Not Implemented |
ND0209 # 05 Y:1995 | 05 | 1995 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $900 | $938 | Not Implemented |
ND0209 # 06 Y:1995 | 06 | 1995 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $4,749 | $7,975 | Implemented |
ND0209 # 07 Y:1995 | 07 | 1995 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $2,157 | $3,720 | Not Implemented |
ND0209 # 08 Y:1995 | 08 | 1995 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $525 | $1,400 | Not Implemented |
ND0209 # 09 Y:1995 | 09 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $151 | $520 | Not Implemented |
IA0111 # 01 Y:1995 | 01 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $20,199 | $58,658 | Not Implemented |
IA0111 # 02 Y:1995 | 02 | 1995 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $3,310 | $3,860 | Not Implemented |
IA0111 # 03 Y:1995 | 03 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,777 | $9,655 | Implemented |
IA0111 # 04 Y:1995 | 04 | 1995 | INSTALL OCCUPANCY SENSORS | $1,159 | $1,609 | Not Implemented |
IA0111 # 05 Y:1995 | 05 | 1995 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,029 | $500 | Implemented |
IA0111 # 06 Y:1995 | 06 | 1995 | CONVERT TO HIGH VOLUME LOW PRESSURE (HVLP) PAINT GUNS | $11,610 | $1,200 | Not Implemented |
IA0111 # 07 Y:1995 | 07 | 1995 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $2,022 | $1,716 | Not Implemented |
IA0111 # 08 Y:1995 | 08 | 1995 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $1,672 | $8,000 | Implemented |
UM0025 # 01 Y:1995 | 01 | 1995 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,153 | $1,216 | Not Implemented |
UM0025 # 02 Y:1995 | 02 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $15,607 | $28,762 | Not Implemented |
UM0025 # 03 Y:1995 | 03 | 1995 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $4,494 | $3,000 | Not Implemented |
UM0025 # 04 Y:1995 | 04 | 1995 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $1,581 | $0 | Not Implemented |
UM0025 # 05 Y:1995 | 05 | 1995 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT INCOMING FLUIDS | $6,138 | $1,500 | Not Implemented |
AS0144 # 01 Y:1995 | 01 | 1995 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $42,045 | $63,900 | Implemented |
AS0144 # 02 Y:1995 | 02 | 1995 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $22,768 | $58,000 | Not Implemented |