Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
132
matching recommendationsSIC | 371 | Motor Vehicles And Equipment |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
GT0794 # 09 Y:2004 | 09 | 2004 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $3,609 | $0 | Implemented |
GT0794 # 08 Y:2004 | 08 | 2004 | RECOVER WASTE HEAT FROM EQUIPMENT | $8,773 | $4,900 | Not Implemented |
GT0794 # 07 Y:2004 | 07 | 2004 | INSTALL TIMERS AND/OR THERMOSTATS | $729 | $1,500 | Not Implemented |
GT0794 # 06 Y:2004 | 06 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $8,490 | $2,500 | Implemented |
GT0794 # 05 Y:2004 | 05 | 2004 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $5,022 | $3,380 | Not Implemented |
GT0794 # 04 Y:2004 | 04 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,306 | $2,046 | Implemented |
GT0794 # 03 Y:2004 | 03 | 2004 | INSTALL OCCUPANCY SENSORS | $595 | $765 | Not Implemented |
GT0794 # 02 Y:2004 | 02 | 2004 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,785 | $3,525 | Not Implemented |
GT0794 # 01 Y:2004 | 01 | 2004 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $15,414 | $30,000 | n/a |
OK0699 # 04 Y:2004 | 04 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,440 | $18,681 | Implemented |
OK0699 # 01 Y:2004 | 01 | 2004 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $9,780 | $6,150 | Implemented |
OK0699 # 02 Y:2004 | 02 | 2004 | AIR CONDITION ONLY SPACE NECESSARY | $8,145 | $24,175 | Implemented |
OK0699 # 06 Y:2004 | 06 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $418 | $520 | Implemented |
OK0699 # 03 Y:2004 | 03 | 2004 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $5,446 | $23,400 | Implemented |
OK0699 # 08 Y:2004 | 08 | 2004 | CHECK FOR ACCURACY OF UTILITY / POWER METERS | $4,470 | $0 | Implemented |
OK0699 # 05 Y:2004 | 05 | 2004 | INSTALL SET-BACK TIMERS | $6,489 | $3,960 | Implemented |
OK0699 # 07 Y:2004 | 07 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $324 | $707 | Implemented |
IA0356 # 06 Y:2004 | 06 | 2004 | INSTALL OCCUPANCY SENSORS | $2,860 | $4,628 | Not Implemented |
IA0356 # 07 Y:2004 | 07 | 2004 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $254 | $120 | Implemented |
IA0356 # 05 Y:2004 | 05 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $536 | $752 | Implemented |
IA0356 # 04 Y:2004 | 04 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,734 | $6,677 | Implemented |
IA0356 # 03 Y:2004 | 03 | 2004 | TURN OFF EQUIPMENT WHEN NOT IN USE | $1,645 | $2,290 | Implemented |
IA0356 # 02 Y:2004 | 02 | 2004 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $2,880 | $200 | Implemented |
IA0356 # 01 Y:2004 | 01 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,212 | $349 | Implemented |
BD0274 # 05 Y:2004 | 05 | 2004 | RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER | $2,571 | $1,000 | Implemented |