Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
865
matching recommendationsSIC | 384 | Medical Instruments And Supplies |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LE0189 # 02 Y:2004 | 02 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $10,542 | $600 | Implemented |
LE0189 # 05 Y:2004 | 05 | 2004 | TURN OFF EQUIPMENT WHEN NOT IN USE | $293 | $0 | Implemented |
AM0463 # 01 Y:2004 | 01 | 2004 | LOWER LIGHT FIXTURES IN HIGH CEILING AREAS | $23,300 | $19,700 | Implemented |
AM0463 # 02 Y:2004 | 02 | 2004 | OPTIMIZE PLANT POWER FACTOR | $18,200 | $16,600 | Implemented |
AM0463 # 04 Y:2004 | 04 | 2004 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $3,100 | $0 | Implemented |
AM0463 # 05 Y:2004 | 05 | 2004 | INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE | $1,475 | $0 | Implemented |
AM0463 # 07 Y:2004 | 07 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,450 | $730 | Implemented |
AM0463 # 08 Y:2004 | 08 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,030 | $400 | Implemented |
SD0339 # 01 Y:2004 | 01 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $15,112 | $320 | Implemented |
SD0339 # 03 Y:2004 | 03 | 2004 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $3,831 | $0 | Implemented |
SD0325 # 02 Y:2003 | 02 | 2003 | TURN OFF EQUIPMENT WHEN NOT IN USE | $71,754 | $0 | Implemented |
SD0325 # 03 Y:2003 | 03 | 2003 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $53,956 | $32,725 | Implemented |
SD0325 # 04 Y:2003 | 04 | 2003 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $37,849 | $2,000 | Implemented |
SD0325 # 05 Y:2003 | 05 | 2003 | INSTALL TIMERS AND/OR THERMOSTATS | $36,071 | $1,000 | Implemented |
LE0156 # 01 Y:2003 | 01 | 2003 | SIZE AIR HANDLING GRILLS/ DUCT/S COILS TO MINIMIZE AIR RESISTANCE | $1,112 | $870 | Implemented |
LE0156 # 04 Y:2003 | 04 | 2003 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $2,340 | $0 | Implemented |
LE0156 # 05 Y:2003 | 05 | 2003 | INSULATE BARE EQUIPMENT | $1,413 | $0 | Implemented |
LE0156 # 07 Y:2003 | 07 | 2003 | INSTALL OCCUPANCY SENSORS | $239 | $600 | Implemented |
AM0437 # 01 Y:2003 | 01 | 2003 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $10,100 | $0 | Implemented |
AM0437 # 02 Y:2003 | 02 | 2003 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,670 | $1,900 | Implemented |
AM0437 # 04 Y:2003 | 04 | 2003 | INSULATE BARE EQUIPMENT | $4,480 | $1,380 | Implemented |
AM0437 # 05 Y:2003 | 05 | 2003 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $2,110 | $0 | Implemented |
AM0437 # 07 Y:2003 | 07 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $975 | $785 | Implemented |
AM0437 # 08 Y:2003 | 08 | 2003 | USE PHOTOCELL CONTROLS | $1,110 | $110 | Implemented |
AM0437 # 09 Y:2003 | 09 | 2003 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $3,464 | $350 | Implemented |