Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
32
matching recommendationsSIC | 39 | Miscellaneous Manufacturing Industries |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OR0805 # 02 Y:2025 | 02 | 2025 | MINIMIZE OPERATION OF EQUIPMENT MAINTAINED IN STANDBY CONDITION | $2,187 | $0 | n/a |
OR0805 # 01 Y:2025 | 01 | 2025 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $26,892 | $0 | n/a |
OR0805 # 03 Y:2025 | 03 | 2025 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $928 | $0 | n/a |
OR0805 # 04 Y:2025 | 04 | 2025 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $4,157 | $3,706 | n/a |
OR0805 # 05 Y:2025 | 05 | 2025 | REGRIND, REUSE, OR SELL SCRAP PLASTIC PARTS | $5,605 | $0 | n/a |
OR0805 # 06 Y:2025 | 06 | 2025 | USE SOLAR HEAT TO MAKE ELECTRICTY | $103,946 | $1,750,000 | n/a |
OR0743 # 01 Y:2021 | 01 | 2021 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $46,625 | $0 | Implemented |
OR0743 # 03 Y:2021 | 03 | 2021 | STORE HEATED/ COOLED WATER FOR USE DURING PEAK DEMAND PERIODS | $29,553 | $281,475 | Implemented |
OR0743 # 02 Y:2021 | 02 | 2021 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $4,808 | $8,548 | Implemented |
OR0343 # 01 Y:1999 | 01 | 1999 | AUTOMATE FINISHING PROCESS | $290,000 | $165,000 | Not Implemented |
OR0343 # 09 Y:1999 | 09 | 1999 | RECYCLE CLEANING SOLVENT AND REUSE | $4,540 | $6,000 | Not Implemented |
OR0343 # 08 Y:1999 | 08 | 1999 | OPTIMIZE PLANT POWER FACTOR | $360 | $1,000 | Not Implemented |
OR0343 # 07 Y:1999 | 07 | 1999 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $403 | $0 | Not Implemented |
OR0343 # 06 Y:1999 | 06 | 1999 | UPGRADE CONTROLS ON COMPRESSORS | $1,746 | $0 | Not Implemented |
OR0343 # 05 Y:1999 | 05 | 1999 | ELIMINATE/REDUCE REDUNDANT INSPECTIONS | $17,775 | $250 | Not Implemented |
OR0343 # 04 Y:1999 | 04 | 1999 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $37,500 | $50,000 | Implemented |
OR0343 # 03 Y:1999 | 03 | 1999 | AUTOMATE FINISHING PROCESS | $39,300 | $32,000 | Not Implemented |
OR0343 # 02 Y:1999 | 02 | 1999 | MODIFY CURRENT INCENTIVE PROGRAM | $45,000 | $23,000 | Implemented |
OR0306 # 02 Y:1997 | 02 | 1997 | LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER | $2,780 | $0 | Implemented |
OR0306 # 01 Y:1997 | 01 | 1997 | ELIMINATE OLD STOCK AND MODIFY INVENTORY CONTROL | $18,000 | $0 | Not Implemented |
OR0306 # 03 Y:1997 | 03 | 1997 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $18,530 | $5,000 | Not Implemented |
OR0306 # 05 Y:1997 | 05 | 1997 | UPGRADE OBSOLETE EQUIPMENT | $80 | $0 | Implemented |
OR0306 # 04 Y:1997 | 04 | 1997 | DISCONNECT BALLASTS | $2,422 | $3,120 | Not Implemented |
OR0252 # 03 Y:1995 | 03 | 1995 | REDUCE SCRAP PRODUCTION | $12,740 | $0 | Not Implemented |
OR0252 # 02 Y:1995 | 02 | 1995 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $895 | $1,734 | Implemented |