Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
2,323
matching recommendationsSIC | 49 | Electric, Gas, And Sanitary Services |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
TT0211 # 03 Y:2018 | 03 | 2018 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $89,245 | $600,000 | Not Implemented |
TT0211 # 04 Y:2018 | 04 | 2018 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $73,737 | $75,000 | Not Implemented |
TT0211 # 05 Y:2018 | 05 | 2018 | USE OPTIMUM TEMPERATURE | $67,812 | $300,000 | Not Implemented |
TT0211 # 06 Y:2018 | 06 | 2018 | USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY | $25,620 | $100 | Not Implemented |
TT0211 # 07 Y:2018 | 07 | 2018 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $13,109 | $3,750 | Implemented |
IC0209 # 01 Y:2018 | 01 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,273 | $4,939 | Implemented |
IC0209 # 02 Y:2018 | 02 | 2018 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $4,222 | $11,728 | Not Implemented |
IC0209 # 03 Y:2018 | 03 | 2018 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $32,608 | $764 | Not Implemented |
UK1810 # 01 Y:2018 | 01 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,656 | $10,541 | Implemented |
UK1810 # 02 Y:2018 | 02 | 2018 | ELIMINATE/REDUCE AN OPERATION | $21,029 | $10,000 | Not Implemented |
UK1810 # 03 Y:2018 | 03 | 2018 | USE ONLY CERTIFIED MOTOR REPAIR SHOPS | $902 | $2,215 | Implemented |
UK1810 # 04 Y:2018 | 04 | 2018 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $36,700 | $5,900 | Implemented |
UK1810 # 05 Y:2018 | 05 | 2018 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $1,415 | $0 | Implemented |
UK1810 # 06 Y:2018 | 06 | 2018 | REPLACE TREATED WATER WITH WELL / SURFACE WATER | $22,528 | $8,200 | Implemented |
UK1809 # 01 Y:2018 | 01 | 2018 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $1,241 | $2,280 | Implemented |
UK1809 # 02 Y:2018 | 02 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,335 | $2,549 | Implemented |
UK1809 # 03 Y:2018 | 03 | 2018 | TURN OFF EQUIPMENT WHEN NOT IN USE | $70,852 | $4,650 | Implemented |
UK1809 # 04 Y:2018 | 04 | 2018 | USE ONLY CERTIFIED MOTOR REPAIR SHOPS | $846 | $1,257 | Implemented |
UK1809 # 05 Y:2018 | 05 | 2018 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,001 | $64 | Implemented |
UK1809 # 06 Y:2018 | 06 | 2018 | DEVELOP A REPAIR/REPLACE POLICY | $9,600 | $6,502 | Not Implemented |
UK1808 # 01 Y:2018 | 01 | 2018 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $247 | $0 | Implemented |
UK1808 # 02 Y:2018 | 02 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $459 | $516 | Implemented |
UK1808 # 03 Y:2018 | 03 | 2018 | INSTALL OCCUPANCY SENSORS | $246 | $133 | Implemented |
UK1808 # 04 Y:2018 | 04 | 2018 | TURN OFF EQUIPMENT WHEN NOT IN USE | $5,751 | $0 | Implemented |
UK1808 # 05 Y:2018 | 05 | 2018 | REPLACE TREATED WATER WITH WELL / SURFACE WATER | $11,910 | $3,700 | Not Implemented |