Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
66,998
matching recommendationsARC | 2 | ENERGY MANAGEMENT |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UW2309 # 03 Y:2023 | 03 | 2023 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $6,805 | $0 | Implemented |
OR0773 # 01 Y:2023 | 01 | 2023 | USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS | $5,439 | $1,278 | Implemented |
OR0773 # 02 Y:2023 | 02 | 2023 | INSTALL / REPAIR INSULATION ON STEAM LINES | $1,051 | $797 | Implemented |
NT0014 # 01 Y:2023 | 01 | 2023 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $9,483 | $1,258 | Implemented |
NT0014 # 02 Y:2023 | 02 | 2023 | CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD | $6,006 | $6,160 | Implemented |
NT0014 # 03 Y:2023 | 03 | 2023 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $955 | $0 | Implemented |
NT0014 # 04 Y:2023 | 04 | 2023 | OPTIMIZE PLANT POWER FACTOR | $2,486 | $1,441 | Implemented |
NT0014 # 05 Y:2023 | 05 | 2023 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $5,512 | $0 | Implemented |
LS2315 # 01 Y:2023 | 01 | 2023 | INSTALL OCCUPANCY SENSORS | $5,741 | $690 | Implemented |
LS2315 # 03 Y:2023 | 03 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,010 | $915 | Implemented |
LS2315 # 04 Y:2023 | 04 | 2023 | INSTALL OCCUPANCY SENSORS | $118 | $190 | Implemented |
LS2314 # 01 Y:2023 | 01 | 2023 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $1,310 | $0 | Implemented |
LS2314 # 02 Y:2023 | 02 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,404 | $135 | Implemented |
LS2314 # 04 Y:2023 | 04 | 2023 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $12,651 | $11,390 | Implemented |
IC0288 # 02 Y:2023 | 02 | 2023 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $137 | $78 | Implemented |
IC0288 # 05 Y:2023 | 05 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,633 | $4,136 | Implemented |
IC0288 # 06 Y:2023 | 06 | 2023 | INSTALL / REPAIR INSULATION ON STEAM LINES | $592 | $496 | Implemented |
DL0225 # 01 Y:2023 | 01 | 2023 | REMOVE OR CLOSE OFF UNNEEDED COMPRESSED AIR LINES | $6,327 | $0 | Implemented |
DL0225 # 02 Y:2023 | 02 | 2023 | REMOVE OR CLOSE OFF UNNEEDED COMPRESSED AIR LINES | $6,327 | $0 | Implemented |
DL0225 # 03 Y:2023 | 03 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,072 | $500 | Implemented |
DL0225 # 08 Y:2023 | 08 | 2023 | RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER | $9,068 | $28,750 | Implemented |
MI0427 # 01 Y:2023 | 01 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $18,053 | $1,060 | Implemented |
MI0427 # 03 Y:2023 | 03 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $7,069 | $4,697 | Implemented |
MI0427 # 07 Y:2023 | 07 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,803 | $791 | Implemented |
LS2313 # 01 Y:2023 | 01 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $6,049 | $50 | Implemented |