Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
67,054
matching recommendationsARC | 2 | ENERGY MANAGEMENT |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OR0678 # 03 Y:2016 | 03 | 2016 | INSULATE BARE EQUIPMENT | $972 | $2,626 | Implemented |
SU0421 # 01 Y:2016 | 01 | 2016 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $31 | $0 | Implemented |
SU0421 # 02 Y:2016 | 02 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $554 | $340 | Implemented |
SU0421 # 03 Y:2016 | 03 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $73 | $74 | Implemented |
SU0421 # 07 Y:2016 | 07 | 2016 | INSTALL OCCUPANCY SENSORS | $59 | $290 | Implemented |
UD0957 # 02 Y:2016 | 02 | 2016 | VENTILATION SYSTEM TO SHUT OFF WHEN ROOM IS NOT IN USE | $7,063 | $0 | Implemented |
UD0957 # 04 Y:2016 | 04 | 2016 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,213 | $0 | Implemented |
UD0957 # 06 Y:2016 | 06 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $29,859 | $86,636 | Implemented |
UD0957 # 07 Y:2016 | 07 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,818 | $6,804 | Implemented |
WV0535 # 02 Y:2016 | 02 | 2016 | INSULATE BARE EQUIPMENT | $4,153 | $511 | Implemented |
WV0535 # 03 Y:2016 | 03 | 2016 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $3,206 | $1,000 | Implemented |
WV0535 # 06 Y:2016 | 06 | 2016 | DEVELOP A REPAIR/REPLACE POLICY | $1,538 | $578 | Implemented |
WV0535 # 07 Y:2016 | 07 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,622 | $2,120 | Implemented |
WV0535 # 08 Y:2016 | 08 | 2016 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $691 | $30 | Implemented |
WV0535 # 09 Y:2016 | 09 | 2016 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $320 | $298 | Implemented |
WV0535 # 10 Y:2016 | 10 | 2016 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $260 | $138 | Implemented |
WV0534 # 02 Y:2016 | 02 | 2016 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $3,016 | $0 | Implemented |
WV0534 # 03 Y:2016 | 03 | 2016 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $2,083 | $1,000 | Implemented |
WV0534 # 04 Y:2016 | 04 | 2016 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $2,026 | $4,100 | Implemented |
WV0534 # 07 Y:2016 | 07 | 2016 | INSULATE BARE EQUIPMENT | $1,196 | $1,953 | Implemented |
WV0534 # 08 Y:2016 | 08 | 2016 | INSTALL OCCUPANCY SENSORS | $616 | $315 | Implemented |
WV0534 # 09 Y:2016 | 09 | 2016 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $474 | $256 | Implemented |
WV0534 # 10 Y:2016 | 10 | 2016 | DEVELOP A REPAIR/REPLACE POLICY | $471 | $1,125 | Implemented |
WV0534 # 11 Y:2016 | 11 | 2016 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $144 | $50 | Implemented |
OR0677 # 01 Y:2016 | 01 | 2016 | INSULATE BARE EQUIPMENT | $7,372 | $5,408 | Implemented |