Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
142,519
matching recommendationsARC | 2 | ENERGY MANAGEMENT |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UL2316 # 02 Y:2023 | 02 | 2023 | USE OUTSIDE COLD WATER SOURCE AS A SUPPLY OF COOLING WATER | $73,247 | $137,300 | n/a |
UL2316 # 03 Y:2023 | 03 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $112,167 | $989,084 | n/a |
UL2316 # 04 Y:2023 | 04 | 2023 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $7,026 | $0 | n/a |
UL2316 # 05 Y:2023 | 05 | 2023 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $15,036 | $20,000 | n/a |
UL2316 # 06 Y:2023 | 06 | 2023 | INSTALL HYDROGEN FUEL CELL | $281,388 | $1,750,000 | n/a |
UU0240 # 01 Y:2024 | 01 | 2024 | USE COOLING TOWER WATER INSTEAD OF REFRIGERATION | $10,047 | $10,320 | n/a |
UU0240 # 02 Y:2024 | 02 | 2024 | INCREASE AMOUNT OF CONDENSATE RETURNED | $1,601 | $7,755 | n/a |
UU0240 # 03 Y:2024 | 03 | 2024 | TURN OFF EQUIPMENT WHEN NOT IN USE | $1,286 | $1,500 | n/a |
UU0240 # 04 Y:2024 | 04 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $977 | $113 | n/a |
UU0240 # 05 Y:2024 | 05 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $544 | $1,387 | n/a |
WM0210 # 01 Y:2024 | 01 | 2024 | OPTIMIZE PLANT POWER FACTOR | $12,043 | $21,250 | n/a |
WM0210 # 02 Y:2024 | 02 | 2024 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $8,116 | $0 | n/a |
WM0210 # 03 Y:2024 | 03 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $4,452 | $0 | n/a |
WM0210 # 04 Y:2024 | 04 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,808 | $1,400 | n/a |
WM0210 # 05 Y:2024 | 05 | 2024 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,410 | $7,096 | n/a |
WM0210 # 06 Y:2024 | 06 | 2024 | INSTALL OCCUPANCY SENSORS | $2,041 | $278 | n/a |
WM0210 # 07 Y:2024 | 07 | 2024 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $566 | $1,050 | n/a |
WM0210 # 08 Y:2024 | 08 | 2024 | REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | $564 | $1,417 | n/a |
WM0210 # 09 Y:2024 | 09 | 2024 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $277 | $0 | n/a |
LE0557 # 01 Y:2024 | 01 | 2024 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $279,544 | $0 | n/a |
LE0557 # 02 Y:2024 | 02 | 2024 | INSTALL TIMERS AND/OR THERMOSTATS | $87,150 | $3,000 | n/a |
LE0557 # 03 Y:2024 | 03 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,494 | $100 | n/a |
LE0557 # 04 Y:2024 | 04 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $35,783 | $9,500 | n/a |
LE0557 # 05 Y:2024 | 05 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $197,906 | $323,780 | n/a |
LE0557 # 06 Y:2024 | 06 | 2024 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $291,977 | $600,000 | n/a |