IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

1,875

matching recommendations
Reset
ARC 2. ENERGY MANAGEMENT
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
AM0630 # 07 Y:2013 07 2013 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $5,240 $350 Implemented
SU0331 # 01 Y:2013 01 2013 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE $808 $0 Implemented
SU0331 # 02 Y:2013 02 2013 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE $211 $0 Implemented
SU0331 # 03 Y:2013 03 2013 CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES $19 $0 Implemented
SU0331 # 04 Y:2013 04 2013 INSTALL SET-BACK TIMERS $299 $228 Implemented
SU0331 # 05 Y:2013 05 2013 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $142 $299 Implemented
SF0425 # 01 Y:2013 01 2013 USE DRYING OVEN (BATCH TYPE) ON ALTERNATE DAYS OR OTHER OPTIMUM SCHEDULE TO RUN EQUIPMENT WITH FULL LOADS $6,713 $0 Implemented
SF0425 # 02 Y:2013 02 2013 USE / PURCHASE OPTIMUM SIZED COMPRESSOR $15,421 $7,471 Implemented
SF0425 # 06 Y:2013 06 2013 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,808 $7,235 Implemented
SF0425 # 07 Y:2013 07 2013 INSTALL OCCUPANCY SENSORS $3,416 $13,849 Implemented
SF0425 # 08 Y:2013 08 2013 HEAT WATER DURING OFF-PEAK PERIODS AND STORE FOR LATER USE $692 $2,830 Implemented
IA0492 # 01 Y:2013 01 2013 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,544 $585 Implemented
IA0492 # 02 Y:2013 02 2013 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES $4,344 $720 Implemented
IA0492 # 03 Y:2013 03 2013 INSTALL OCCUPANCY SENSORS $755 $1,617 Implemented
LE0352 # 05 Y:2013 05 2013 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $2,414 $2,750 Implemented
OK0839 # 01 Y:2013 01 2013 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $7,514 $27,500 Implemented
OK0839 # 02 Y:2013 02 2013 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $3,540 $0 Implemented
OK0839 # 03 Y:2013 03 2013 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,395 $1,750 Implemented
OK0839 # 04 Y:2013 04 2013 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $7,494 $33,218 Implemented
OK0839 # 07 Y:2013 07 2013 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL $2,708 $5,684 Implemented
OK0839 # 09 Y:2013 09 2013 CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS $873 $490 Implemented
OK0839 # 11 Y:2013 11 2013 SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY $32,511 $25,606 Implemented
OK0839 # 13 Y:2013 13 2013 OPTIMIZE PLANT POWER FACTOR $12,090 $11,638 Implemented
BS0012 # 01 Y:2013 01 2013 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $1,483 $900 Implemented
BS0012 # 02 Y:2013 02 2013 TURN OFF EQUIPMENT WHEN NOT IN USE $3,601 $8,272 Implemented