Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
4,391
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
BD0123 # 04 Y:1998 | 04 | 1998 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $763 | $200 | Implemented |
BD0123 # 05 Y:1998 | 05 | 1998 | INSTALL OCCUPANCY SENSORS | $714 | $400 | Not Implemented |
BD0123 # 06 Y:1998 | 06 | 1998 | USE SYNTHETIC LUBRICANT | $555 | $300 | Not Implemented |
BD0123 # 07 Y:1998 | 07 | 1998 | CONVERT TO HIGH VOLUME LOW PRESSURE (HVLP) PAINT GUNS | $44,117 | $14,500 | Not Implemented |
BD0123 # 08 Y:1998 | 08 | 1998 | MINIMIZE WATER USAGE | $259 | $620 | Not Implemented |
BD0123 # 09 Y:1998 | 09 | 1998 | PAY BILLS ON TIME TO AVOID LATE FEES | $533 | $0 | Implemented |
BD0122 # 01 Y:1998 | 01 | 1998 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,044 | $12,900 | Not Implemented |
BD0122 # 02 Y:1998 | 02 | 1998 | USE RADIANT HEATER FOR SPOT HEATING | $3,315 | $7,200 | Not Implemented |
BD0122 # 03 Y:1998 | 03 | 1998 | INSTALL OCCUPANCY SENSORS | $2,196 | $1,350 | Not Implemented |
BD0122 # 04 Y:1998 | 04 | 1998 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,934 | $750 | Implemented |
BD0122 # 05 Y:1998 | 05 | 1998 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $351 | $250 | Implemented |
BD0122 # 06 Y:1998 | 06 | 1998 | INSULATE FEEDWATER TANK | $56,279 | $15,800 | Not Implemented |
BD0122 # 07 Y:1998 | 07 | 1998 | LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER | $8,070 | $8,000 | Not Implemented |
BD0122 # 08 Y:1998 | 08 | 1998 | AUTOMATE FINISHING PROCESS | $12,828 | $25,000 | Not Implemented |
BD0122 # 09 Y:1998 | 09 | 1998 | PAY BILLS ON TIME TO AVOID LATE FEES | $313 | $0 | Implemented |
BD0121 # 01 Y:1998 | 01 | 1998 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $1,994 | $1,500 | Not Implemented |
BD0121 # 02 Y:1998 | 02 | 1998 | INSTALL OCCUPANCY SENSORS | $1,529 | $675 | Implemented |
BD0121 # 03 Y:1998 | 03 | 1998 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,482 | $400 | Not Implemented |
BD0121 # 04 Y:1998 | 04 | 1998 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $1,472 | $1,600 | Implemented |
BD0121 # 05 Y:1998 | 05 | 1998 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $836 | $1,400 | Implemented |
BD0121 # 06 Y:1998 | 06 | 1998 | CONVERT TO HIGH VOLUME LOW PRESSURE (HVLP) PAINT GUNS | $11,391 | $3,000 | Not Implemented |
BD0121 # 07 Y:1998 | 07 | 1998 | LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER | $3,914 | $8,000 | Implemented |
BD0121 # 08 Y:1998 | 08 | 1998 | MODIFY PROCESS TO REDUCE MATERIAL USE/COST | $771 | $500 | Implemented |
BD0121 # 09 Y:1998 | 09 | 1998 | PAY BILLS ON TIME TO AVOID LATE FEES | $404 | $0 | Implemented |
BD0120 # 01 Y:1998 | 01 | 1998 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $13,459 | $600 | Implemented |