IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

125

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
BD0452 # 02 Y:2014 02 2014 INSTALL OCCUPANCY SENSORS $2,841 $750 Not Implemented
BD0452 # 08 Y:2014 08 2014 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $600 $435 Implemented
BD0452 # 03 Y:2014 03 2014 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,830 $600 Implemented
BD0452 # 07 Y:2014 07 2014 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $823 $300 Not Implemented
BD0452 # 04 Y:2014 04 2014 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $2,291 $20 Not Implemented
BD0452 # 05 Y:2014 05 2014 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,686 $1,310 Not Implemented
BD0452 # 06 Y:2014 06 2014 USE RADIANT HEATER FOR SPOT HEATING $909 $3,300 Not Implemented
BD0452 # 01 Y:2014 01 2014 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,825 $4,565 Not Implemented
BD0452 # 09 Y:2014 09 2014 CONTRACT A WOOD PALLET RECYCLING COMPANY $2,911 $80 Not Implemented
BD0316 # 04 Y:2006 04 2006 INSTALL OCCUPANCY SENSORS $1,033 $675 Implemented
BD0316 # 01 Y:2006 01 2006 USE SYNTHETIC LUBRICANT $7,871 $800 Not Implemented
BD0316 # 02 Y:2006 02 2006 COOL COMPRESSOR AIR INTAKE WITH HEAT EXCHANGER $4,724 $1,200 Implemented
BD0316 # 03 Y:2006 03 2006 LOWER LIGHT FIXTURES IN HIGH CEILING AREAS $13,153 $8,363 Implemented
BD0316 # 05 Y:2006 05 2006 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $679 $2,102 Implemented
BD0313 # 07 Y:2006 07 2006 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,780 $800 Implemented
BD0313 # 01 Y:2006 01 2006 RECOVER WASTE HEAT FROM EQUIPMENT $180,015 $152 Implemented
BD0313 # 09 Y:2006 09 2006 INSTALL OCCUPANCY SENSORS $3,815 $1,275 Implemented
BD0313 # 08 Y:2006 08 2006 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $10,038 $10,039 Implemented
BD0313 # 05 Y:2006 05 2006 INSTALL TURBULATORS $2,094 $1,500 Implemented
BD0313 # 02 Y:2006 02 2006 RECOVER WASTE HEAT FROM EQUIPMENT $12,962 $5,000 Implemented
BD0313 # 06 Y:2006 06 2006 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $3,516 $0 Not Implemented
BD0313 # 03 Y:2006 03 2006 MAKE ICE DURING OFF PEAK HOURS FOR COOLING $162,249 $310,000 Not Implemented
BD0313 # 04 Y:2006 04 2006 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $13,938 $0 Implemented
BD0305 # 02 Y:2006 02 2006 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,132 $1,000 Implemented
BD0305 # 03 Y:2006 03 2006 INSTALL OCCUPANCY SENSORS $2,072 $225 Not Implemented