Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
4,715
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
CO0530 # 03 Y:2003 | 03 | 2003 | UPGRADE CONTROLS ON COMPRESSORS | $2,940 | $280 | Implemented |
CO0530 # 04 Y:2003 | 04 | 2003 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,070 | $7,760 | Implemented |
CO0530 # 05 Y:2003 | 05 | 2003 | INSTALL OCCUPANCY SENSORS | $1,830 | $4,140 | Not Implemented |
CO0530 # 06 Y:2003 | 06 | 2003 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,810 | $1,250 | Implemented |
CO0530 # 07 Y:2003 | 07 | 2003 | INSTALL SPECTRAL REFLECTORS / DELAMP | $1,200 | $570 | Not Implemented |
CO0530 # 08 Y:2003 | 08 | 2003 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $4,089,000 | $4,200,000 | Not Implemented |
CO0526 # 01 Y:2003 | 01 | 2003 | USE OPTIMUM SIZE AND CAPACITY EQUIPMENT | $21,790 | $37,580 | Implemented |
CO0526 # 02 Y:2003 | 02 | 2003 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $13,240 | $33,710 | Implemented |
CO0526 # 03 Y:2003 | 03 | 2003 | INSTALL SPECTRAL REFLECTORS / DELAMP | $8,350 | $1,640 | Not Implemented |
CO0526 # 04 Y:2003 | 04 | 2003 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $8,180 | $3,150 | Implemented |
CO0526 # 05 Y:2003 | 05 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,602 | $5,670 | Implemented |
CO0526 # 06 Y:2003 | 06 | 2003 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $3,060 | $580 | Not Implemented |
CO0526 # 07 Y:2003 | 07 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,398 | $6,640 | Not Implemented |
CO0526 # 08 Y:2003 | 08 | 2003 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $980 | $3,300 | Implemented |
CO0526 # 09 Y:2003 | 09 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $320 | $586 | Not Implemented |
CO0521 # 01 Y:2003 | 01 | 2003 | UTILIZE A LESS EXPENSIVE COOLING METHOD | $65,190 | $82,000 | Not Implemented |
CO0521 # 02 Y:2003 | 02 | 2003 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,840 | $5,100 | Not Implemented |
CO0521 # 03 Y:2003 | 03 | 2003 | USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER | $2,010 | $1,400 | Implemented |
CO0521 # 04 Y:2003 | 04 | 2003 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,000 | $200 | Implemented |
CO0521 # 05 Y:2003 | 05 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,650 | $3,532 | Not Implemented |
CO0521 # 06 Y:2003 | 06 | 2003 | USE COMBINED CYCLE GAS TURBINE GENERATOR SETS WITH WASTE HEAT BOILERS CONNECTED TO TURBINE EXHAUST | $48,290 | $175,000 | Not Implemented |
CO0523 # 01 Y:2003 | 01 | 2003 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $19,740 | $12,000 | Not Implemented |
CO0523 # 02 Y:2003 | 02 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $10,270 | $19,440 | Not Implemented |
CO0523 # 03 Y:2003 | 03 | 2003 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,990 | $230 | Implemented |
CO0523 # 04 Y:2003 | 04 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,122 | $12,500 | Not Implemented |