Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
155
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
DS0092 # 07 Y:1997 | 07 | 1997 | $12,302 | $5,500 | Implemented | |
DS0092 # 06 Y:1997 | 06 | 1997 | USE A RAG RECYCLE SERVICE | $227 | $750 | Not Implemented |
DS0092 # 05 Y:1997 | 05 | 1997 | CONVERT TO HIGH VOLUME LOW PRESSURE (HVLP) PAINT GUNS | $2,123 | $700 | Not Implemented |
DS0092 # 04 Y:1997 | 04 | 1997 | INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS | $1,905 | $2,100 | Not Implemented |
DS0092 # 03 Y:1997 | 03 | 1997 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $134 | $182 | Implemented |
DS0092 # 02 Y:1997 | 02 | 1997 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $327 | $280 | Implemented |
DS0092 # 01 Y:1997 | 01 | 1997 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,439 | $2,055 | Not Implemented |
DS0091 # 06 Y:1997 | 06 | 1997 | REDUCE DELIVERY SCHEDULES | $71,460 | $50,000 | Implemented |
DS0091 # 05 Y:1997 | 05 | 1997 | USE OTHER WASTE CONCENTRATION METHODS | $1,784 | $10,000 | Not Implemented |
DS0091 # 04 Y:1997 | 04 | 1997 | REGRIND, REUSE, OR SELL SCRAP PLASTIC PARTS | $760 | $800 | Not Implemented |
DS0091 # 03 Y:1997 | 03 | 1997 | USE "HEAT WHEEL" OR OTHER HEAT EXCHANGER TO CROSS-EXCHANGE BUILDING EXHAUST AIR WITH MAKE-UP AIR | $121,380 | $250,000 | Implemented |
DS0091 # 02 Y:1997 | 02 | 1997 | INSULATE BARE EQUIPMENT | $3,234 | $882 | Implemented |
DS0091 # 01 Y:1997 | 01 | 1997 | INSTALL OCCUPANCY SENSORS | $886 | $900 | Not Implemented |
DS0090 # 08 Y:1997 | 08 | 1997 | $70,200 | $65,000 | Implemented | |
DS0090 # 07 Y:1997 | 07 | 1997 | REPLACE GASOLINE WITH DIESEL, LPG, OR NATURAL GAS | $13,750 | $19,000 | Implemented |
DS0090 # 06 Y:1997 | 06 | 1997 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $13,735 | $9,500 | Implemented |
DS0090 # 05 Y:1997 | 05 | 1997 | USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL | $10,196 | $32,400 | Not Implemented |
DS0090 # 04 Y:1997 | 04 | 1997 | UTILIZE A LESS EXPENSIVE COOLING METHOD | $16,937 | $20,000 | Implemented |
DS0090 # 03 Y:1997 | 03 | 1997 | COVER OPEN TANKS | $634 | $242 | Not Implemented |
DS0090 # 02 Y:1997 | 02 | 1997 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $2,210 | $1,910 | Implemented |
DS0090 # 01 Y:1997 | 01 | 1997 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,097 | $1,800 | Implemented |
DS0089 # 01 Y:1997 | 01 | 1997 | OPTIMIZE PLANT POWER FACTOR | $7,041 | $1,750 | Implemented |
DS0089 # 02 Y:1997 | 02 | 1997 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $296 | $450 | Not Implemented |
DS0089 # 03 Y:1997 | 03 | 1997 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $1,298 | $1,100 | Implemented |
DS0089 # 06 Y:1997 | 06 | 1997 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $41,641 | $2,315 | Implemented |