Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
672
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
HO0221 # 06 Y:2000 | 06 | 2000 | USE DOUBLE OR TRIPLE GLAZED WINDOWS TO MAINTAIN HIGHER RELATIVE HUMIDITY AND TO REDUCE HEAT LOSSES | $2,845 | $9,720 | Implemented |
HO0221 # 05 Y:2000 | 05 | 2000 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $8,721 | $600 | Implemented |
HO0221 # 03 Y:2000 | 03 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,110 | $7,590 | Implemented |
HO0221 # 02 Y:2000 | 02 | 2000 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $554 | $200 | Implemented |
HO0214 # 09 Y:1999 | 09 | 1999 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $1,800 | $120 | Implemented |
HO0213 # 01 Y:1999 | 01 | 1999 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $931 | $0 | Implemented |
HO0212 # 10 Y:1999 | 10 | 1999 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $6,379 | $500 | Implemented |
HO0212 # 08 Y:1999 | 08 | 1999 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $11,437 | $2,882 | Implemented |
HO0212 # 06 Y:1999 | 06 | 1999 | INSTALL / REPAIR INSULATION ON STEAM LINES | $1,548 | $2,882 | Implemented |
HO0212 # 02 Y:1999 | 02 | 1999 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,715 | $400 | Implemented |
HO0211 # 10 Y:1999 | 10 | 1999 | ADD/MODIFY EQUIPMENT TO IMPROVE DRYING PROCESS | $15,600 | $480 | Implemented |
HO0211 # 08 Y:1999 | 08 | 1999 | USE COMPRESSOR AIR FILTERS | $6,130 | $150 | Implemented |
HO0211 # 06 Y:1999 | 06 | 1999 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,539 | $200 | Implemented |
HO0211 # 05 Y:1999 | 05 | 1999 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $900 | $2,000 | Implemented |
HO0211 # 04 Y:1999 | 04 | 1999 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,364 | $20 | Implemented |
HO0211 # 03 Y:1999 | 03 | 1999 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,289 | $1,500 | Implemented |
HO0211 # 02 Y:1999 | 02 | 1999 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $4,114 | $9,233 | Implemented |
HO0211 # 01 Y:1999 | 01 | 1999 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,520 | $15,297 | Implemented |
HO0209 # 03 Y:1999 | 03 | 1999 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,540 | $570 | Implemented |
HO0209 # 02 Y:1999 | 02 | 1999 | INSTALL OCCUPANCY SENSORS | $1,005 | $1,600 | Implemented |
HO0207 # 04 Y:1999 | 04 | 1999 | TURN OFF EQUIPMENT WHEN NOT IN USE | $2,590 | $0 | Implemented |
HO0207 # 01 Y:1999 | 01 | 1999 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $28,880 | $600 | Implemented |
HO0207 # 02 Y:1999 | 02 | 1999 | TURN OFF EQUIPMENT WHEN NOT IN USE | $11,756 | $15,000 | Implemented |
HO0207 # 03 Y:1999 | 03 | 1999 | INSTALL OCCUPANCY SENSORS | $5,242 | $10,000 | Implemented |
HO0207 # 05 Y:1999 | 05 | 1999 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $590 | $0 | Implemented |